Application of the Woodgrove Staged Flotation Reactor (SFR) Technology at the New Afton Concentrator (48th Annual Canadian Mineral Processors Operators Conference©, Ottawa, Ontario, January 2016)

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 10
- File Size:
- 795 KB
- Publication Date:
- Jan 1, 2016
Abstract
"The New Afton concentrator was commissioned in June 2012, reaching the design milling rate in September 2012. By late 2013, through a campaign of optimization and de-bottlenecking, it was recognized that the installed plant was capable of greatly exceeding the design throughput of 11,700 tpd. Because the value of the metal contained (by increasing the plant feed rate) exceeded the offsetting losses of copper and gold recovery (as the operation moved to a coarser grind), the concentrator feed rate was strategically increased with support of New Gold, while the operations team was given a mandate to evaluate, and then implement, flow sheet options that could re-establish the original design criterion grind target and achieve the corresponding improved recovery. Broadly, the two options implemented were the addition of a tertiary grinding stage consisting of Metso Vertimill® prior to rougher flotation (in order to address the grinding required at increasing throughput by increasing the power), and the addition of three Woodgrove Staged Flotation Reactors (SFR) added to the cleaner circuit after regrind of the rougher concentrate (to address the increased mineral loading to the cleaner circuit). Through test work, it was anticipated that the SFRs would be capable of achieving final concentrate grade in a single pass without the integration of recirculating loads, a strategy sometimes referred to pre-cleaning. This paper describes the expectations generated for the Woodgrove SFR unit operation through pilot plant testing on site, and compares those results with the performance of the expanded circuit that exceeded the original design criterion of P80 160 µm, which was commissioned in the second quarter of 2015.INTRODUCTIONThe New Afton concentrator, located near Kamloops, BC Canada, commenced operation in June 2012. The mill achieved the design throughput of 11,000 tonnes per day average during the month of September 2012 and, following various operational optimization efforts (O’Hara et al, 2015), achieved the design p80 grind size of 160 µm at the design milling rate in July 2013.During August 2013, trials were carried out to determine the throughput rate limits of the mill circuits and to evaluate mill metallurgical performance at higher rates. Milling rates up to 15,500 dmt per 24 hours were achieved during this trial, demonstrating potential capability for sustained milling rates exceeding the nominal design capacity. As was expected, the higher milling rates resulted in a coarsening of the grinding circuit product size, and resulted in marginally lower recoveries in the rougher flotation circuit. Despite the lower recoveries, the higher milling rates resulted in higher metal production and the financial analysis favored running at rates of at least 13,000 tonnes per operating day, with the higher cash flow in the near term offsetting the value of metal production loss at the end of the mine life (due to the short term increase in the rate of reserve depletion). Milling rates were sustained above 13,000 tonnes per day through the second half of 2013, and increased above 14,000 tonnes per day by mid-2014 (Figure 1)."
Citation
APA:
(2016) Application of the Woodgrove Staged Flotation Reactor (SFR) Technology at the New Afton Concentrator (48th Annual Canadian Mineral Processors Operators Conference©, Ottawa, Ontario, January 2016)MLA: Application of the Woodgrove Staged Flotation Reactor (SFR) Technology at the New Afton Concentrator (48th Annual Canadian Mineral Processors Operators Conference©, Ottawa, Ontario, January 2016). Canadian Institute of Mining, Metallurgy and Petroleum, 2016.