Atlanta—Plain Train Tunnel West Extension Project— Progressive Design-Build Risk Management Approach - RETC2023

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 10
- File Size:
- 178 KB
- Publication Date:
- Jun 13, 2023
Abstract
Progressive Design-Build is becoming a more common delivery method in the tunneling
industry. This approach allows the Owner to select a design-builder primarily
based on qualification instead of lowest price. The delivery method promotes flexibility
and collaboration at all levels from the initial design stage through construction. Using
the example of the Atlanta Airport Plane Train Tunnel West Extension, value-added
risk management was added during the initial design phase with an independent
reviewer. This paper presents the independent reviewer transitioning from constructability
review in the very early stages of design to independent design verification to
on-site supervision during construction.