Challenges Associated with the Construction of a Cofferdam – A Case Study

Deep Foundations Institute
Khuram R. Mohib Thomas J. Sabourin Eric S. White
Organization:
Deep Foundations Institute
Pages:
10
File Size:
1355 KB
Publication Date:
Jan 1, 2017

Abstract

"This paper presents the challenges associated with the design and construction of a steel sheet pile cofferdam supported with one level of grouted anchors in clean to silty sand with gravel. The initial assessment of the subsurface conditions indicated loose to medium dense soil with intermittent dense to very dense layers with no occurrence of cobbles and boulders. Sheet piles were proposed to be installed to a depth of 24 m below the ground surface to limit dewatering requirements for the cofferdam. During sheet pile installation, refusal of piles occurred at multiple locations forming passages for increased flow into the cofferdam. Modifications were made in the design of the dewatering system as a result of the increased flow. Finite element modeling was used to select the necessary modifications to the dewatering system within the cofferdam. Wells were installed based on the findings of the numerical model. Model simulations showed good comparison with monitoring of the field installed dewatering system.INTRODUCTIONIt is necessary to consider the impact of the ground water, subsurface stratigraphy, strength, and drainage behavior of the soil for the design and construction of cofferdams. This paper presents a case history of the construction of a cofferdam in Northern Ontario, Canada. The project consists of the construction of a powerhouse, intake, and tailrace which will generate around 28 MW of renewable clean energy by diverting water from New Post Creek through a power house and discharge into the Abitibi River. The focus of this paper is the dewatering and excavation support required to permit construction of the powerhouse. The layout of the cofferdam is shown in Fig. 1. The cofferdam for the powerhouse is rectangular in shape with sheet piles on all four sides intended to be driven to the design toe El. 101 m. The east and west walls have a length of 46.3 m. North and south sides are 47.6 m long; and in addition, two cantilever sheet pile walls bound the tailrace on the west side and two cantilever walls were installed on the east for construction of the penstock inlet. The ground surface in the powerhouse cofferdam area, before commencement of sheet pile driving, was brought to El. 125; the ground then slopes up to the East, toward New Post Creek, and the site is bounded on the West by the Abitibi River. 186 pairs of sheet piles were used to create the cofferdam and cantilever walls. The deepest excavation is to elevation 114.4 m. Within the west half of the cofferdam footprint, the base of excavation slopes upward at 3H: 1V to facilitate the tailrace discharge into Abitibi River.SOIL STRATIGRAPHYThe cofferdam design was based on the geotechnical investigation conducted by AECOM (2014) which included two relevant boreholes near the powerhouse footprint. The ground elevation at the time of investigation varied between 131 to 129 m. The material observed to the full depth of investigation was comprised generally of coarse to fine sand and gravelly sand or a sand matrix with gravelly inclusions. Some intermittent layers of clay and silt intrusions were also observed. Generally the soils grade finer away from the river. SPT N60 values were recorded in two borings during the field investigation with values reported from 3 to 92. The in-situ conditions ranged from compact to dense with some loose and some very dense zones. Figure 2 shows the variation in SPT N60 values with elevation."
Citation

APA: Khuram R. Mohib Thomas J. Sabourin Eric S. White  (2017)  Challenges Associated with the Construction of a Cofferdam – A Case Study

MLA: Khuram R. Mohib Thomas J. Sabourin Eric S. White Challenges Associated with the Construction of a Cofferdam – A Case Study. Deep Foundations Institute, 2017.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account