Deep Foundations for Top-Down Construction of High-Rise Project

Deep Foundations Institute
Kenneth S. Hudson Martin B. Hudson Gwendolyn Arreguin
Organization:
Deep Foundations Institute
Pages:
13
File Size:
2123 KB
Publication Date:
Jan 1, 2019

Abstract

A twin high-rise project site in Century City posed several foundation engineering challenges for the design team. One portion of the twin high-rise project site was required to utilize top-down construction in order to allow a driveway to remain open during construction of the project’s 40-foot deep excavation. The challenge was compounded by the need to utilize a mat foundation to support the high-rise construction and yet have temporary drilled shafts through the mat foundation area that would not create excessive differential settlement. This was accomplished by constructing a deck supported by eight drilled end- bearing drilled shafts with Osterberg load cells and five 7-foot-diameter end-bearing drilled shafts. The Osterberg load cells served to verify the capacity of each of the drilled shafts and preload the soils at the drilled shaft tips. The 7-foot-diameter shafts were constructed with bond breakers to prevent skin friction but instead mobilize end bearing (for settlement compatibility with the surrounding mat foundation). After the drilled shafts were placed, then top-down construction began beneath the driveway, leaving the driveway supported on the drilled shafts. Construction challenges included drilling of the shafts through previously abandoned tieback anchors from an adjacent parking structure basement, as well as cemented layers within the rock materials. The paper describes the use of the various analytical methods used to calculate capacities and check settlement compatibility, the construction and testing methods utilized, and the construction challenges encountered. INTRODUCTION Wood Environment and Infrastructure Solutions, Inc. (hereafter referred to as Wood) performed a geotechnical investigation for the New Century Plaza currently being constructed in the Century City District of Los Angeles, California. The New Century Plaza project consists of the construction of two new towers (designated as North and South Buildings) and the rehabilitation of the existing Hyatt Regency Century Plaza Hotel. The existing hotel tower is 15 stories in height above the existing grade and is underlain by four subterranean basement parking levels. The new North and South Buildings will stand approximately 46 stories in height above the existing grade to accommodate residential use. The new towers are planned west of the existing hotel. The site was previously occupied by the existing hotel subterranean parking structure and overlying podium structure, and a loading dock in the southwest portion of the site. The former western portion of the podium and subterranean parking structure west of the existing hotel building western edge were demolished to allow for new subterranean levels, a new podium structure, and the new towers. The lowest floor of the proposed subterranean level required excavation on the order of 35 to 80 feet.
Citation

APA: Kenneth S. Hudson Martin B. Hudson Gwendolyn Arreguin  (2019)  Deep Foundations for Top-Down Construction of High-Rise Project

MLA: Kenneth S. Hudson Martin B. Hudson Gwendolyn Arreguin Deep Foundations for Top-Down Construction of High-Rise Project. Deep Foundations Institute, 2019.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account