Design and Construction of Mixed Ground Working Platform for a CCR Surface Impoundment

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 894 KB
- Publication Date:
- Jan 1, 2019
Abstract
An access pathway and working platform were designed and constructed for equipment access for a Deep Soil Mixing (DSM) pilot study over a coal combustion residual (CCR) surface impoundment (SI). The DSM pilot study was conducted to evaluate slurry mix designs and construction techniques for installing DSM columns up to 95 feet deep. Two-dimensional (2-D) limit equilibrium and 2-D finite element analyses were used to evaluate multiple failure mechanisms including: (i) bearing capacity, (ii) punching shear of mixed ground and underlying CCR, (iii) effect of fluidized DSM columns on working platform stability, and (iv) liquefaction. The analysis results were used to design ground improvement required to increase bearing capacity and stability of the CCR under the proposed equipment access route. A long-reach excavator was used to perform shallow bucket mixing and walk onto the CCR SI atop previously mixed cells following a minimum cure time and acceptance of quality control test results. Prior to mobilizing the DSM rig, a static load test was conducted to evaluate performance of the working platform. Both the access pathway and working platform demonstrated acceptable performance under the design loads during the DSM pilot study. This case study emphasizes the economic and safety benefits that can be realized by appropriately designing critical temporary work items such as access pathways and working platforms in difficult ground conditions.
INTRODUCTION
A Deep Soil Mixing (DSM) pilot study was conducted at a coal combustion residual (CCR) surface impoundment (SI) to evaluate slurry mix designs and construction techniques for closure design of the SI (Site). Sluicing of CCR at the facility ceased and closure will be initiated based on requirements in the final United States Environmental Protection Agency (USEPA) Rule for Disposal of Coal Combustion Residuals from Electric Utilities, 40 CFR 257, effective October 19, 2015. The proposed closure approach involves constructing a DSM containment structure (DSM Wall) to separate the SI into two areas: (i) a closure by removal area; and (ii) a consolidate and cap-in-place area. The proposed DSM Wall would retain the CCR within the consolidated closure footprint and provide a barrier between the two areas of the SI. The predominant CCR in the SI where the pilot study was conducted were fly ash and bottom ash. CCR materials in surface impoundments are generally soft and saturated as a result of being sluiced into place and can present stability and safety challenges when performing earthwork activities.
Citation
APA:
(2019) Design and Construction of Mixed Ground Working Platform for a CCR Surface ImpoundmentMLA: Design and Construction of Mixed Ground Working Platform for a CCR Surface Impoundment. Deep Foundations Institute, 2019.