Dynamic and Static Load Testing: A Cost Savings Approach

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 429 KB
- Publication Date:
- Jan 1, 2019
Abstract
A test pile program was undertaken at a project site in Ain Sukhna, Egypt for an import/export oil jetty. Two 1219 mm diameter open ended steel pipe piles were evaluated at two separate test locations. Each test pile was dynamically tested during initial drive utilizing a Pile Driving Analyzer (PDA). Restrike testing was also performed to evaluate the time dependent soil setup. One static compression test and one static tension test was performed at each test location. A correlation of the static and dynamic load test results was established to develop a driving criteria for the piling across the two kilometer project. The constructability benefits of shorter piles will be discussed in more detail, given that the pile lengths were shortened by 9 to 10 meters on average. Lastly, the use of a four pile linear layout to perform both compression and tension tests will be covered.
INTRODUCTION
With the increased number of Very Large Crude Carriers (VLCC) & Ultra Large Crude Carriers (ULCC) being used to transport oil products around the world, companies and/or nations are presented with the challenge of transferring these products to and from the carriers in deep water scenarios, typically 15 to 20 meter depths, to accommodate the vessels draft. One option for loading/unloading the oil products from a VLCC or ULCC would be to transfer to/from smaller vessels several miles offshore, whereas the most economical option is to unload directly to a pipeline via a berth/jetty platform near shore. These berth platforms must be designed to withstand multiple loading scenarios while these carriers are moored and transferring their products. The use of Large Diameter Open Ended Pipes (LDOEP) piles are a common foundation choice for this offshore application. One of the drawbacks of LDOEP piles, especially across a large project site, is that there can be extreme variability in the pile driving behavior. This can be caused by either a change in soil conditions or the performance of the soil plug. Due to this variability, it is important to verify throughout the duration of the project that the piling is being installed to the correct criteria as established during the load test program. A well designed driven pile load test program, preferably with the combination of Static Load Testing (SLT) and Pile Driving Analysis (PDA), should develop a driving criteria that can allow the contractor and owner to monitor any change in driving behavior.
Citation
APA:
(2019) Dynamic and Static Load Testing: A Cost Savings ApproachMLA: Dynamic and Static Load Testing: A Cost Savings Approach. Deep Foundations Institute, 2019.