Dynamic Pile Testing for the Five Mates Bridge

- Organization:
- Deep Foundations Institute
- Pages:
- 7
- File Size:
- 2178 KB
- Publication Date:
- Jan 1, 1900
Abstract
"This paper will describe dynamic pile testing conducted during installation of driven octagonal precast prestressed concrete piles used as the foundation for this bridge. The piles were long and hence spliced. A number of the piles showed damage near the splices and the damage location was near the ground surface so that the damage could be verified using visual inspection. The piles and splice configuration are still in use today without modification. Further WEAP driveability analysis has been conducted which demonstrates the effect of the splice on pile stresses and a likely failure mode. A slight modification is proposed to the splice that should prevent the damage on future projects.INTRODUCTIONThe bridge site is located on the Olympic Way, Route 41, about 20km north of the regional centre of Albury, NSW. For a long distance north of the site the Olympic Way ""shadows"" the main Melbourne to Sydney rail line and is located on the Western side and in close proximity. At the bridge site there was previously a sharp dog-leg in the road and a right angle level crossing with the road changing to the Eastern side of the rail line, eventually joining up with the Hume Highway, which in turn now becomes a ring-road through the eastern outskirts of Albury. The dog-leg and rail crossing had warning signs and bells, speed restrictions and rumble strips to warn approaching motorists to reduce speed. Site distance was exceptionally good.Approximately 2years before construction a group of five ""high spirited"" young men from the local area were driving south on the Olympic Way adjacent to a south-bound train. It is understood they interacted with the train crew for a period of time. Unfortunately the car and train collided at the level crossing and all of the young men were killed. There were outpourings of grief in the local community and a decision was made to replace the level crossing with a road-over-rail bridge.The bridge was highly skewed with two piers and two high level abutments with fill embankments on both approaches.GROUND CONDITIONSThe site is open grazing country with approximately level ground at the site with surrounding low hills. The geology was unremarkable with consistent stiff clays for a considerable depth.The design required driven precast prestressed pile foundations with the piles to be driven to a considerable depth.Hard driving with high tension stresses were evident from the start of driving and a variety of different pre-bore lengths were adopted in an attempt to minimise driving and potential for damage. At the abutments the pile locations were predrilled for at least the full embankment depth.PILESThe piles were 550mm octagonal prestressed concrete with the pier piles being single piece and the longer abutment piles being two-piece with a ""standard"" epoxy glued box splice. Pier piles and the initial length of the abutment piles were 24m. The add-on piece used at the abutments was 12m. Pile concrete was grade 50MPa."
Citation
APA:
(1900) Dynamic Pile Testing for the Five Mates BridgeMLA: Dynamic Pile Testing for the Five Mates Bridge. Deep Foundations Institute, 1900.