Efficient Deep Foundations, Earth Retention Systems and Ground Improvement – New School Techniques for Columbia Manhattanville’s Subsurface Challenges

Deep Foundations Institute
Di Stasim Jeffrey Frank Di Salvo Justin Lukens
Organization:
Deep Foundations Institute
Pages:
11
File Size:
1079 KB
Publication Date:
Jan 1, 2019

Abstract

Columbia University’s Manhattanville Campus expansion includes the construction of two new business school buildings. The new buildings require development of an entire city block bound by 12th Avenue, W 131st Street, W 130th Street and Broadway in Upper Manhattan. A support of excavation (SOE) package was first released, followed by a foundation package. The SOE package consisted of approximately 100 soldier piles and 280 anchors, up to 215’ long, to support a cut anywhere from 30’- 50’ below street level. The foundation package alone included approximately 1600 drilled micropiles. Given the breadth of the work scope, Hayward Baker Inc and Moretrench joint ventured on these two projects to bring sufficient knowledge and work resources to complete the work in an efficient and timely manner. This included working with the Owner/Engineer to propose different means and methods for construction to significantly reduce the schedule while meeting the design intent, such as large diameter (36” diameter) augercast piles in place of conventionally drilled soldier piles and large hollow-bar micropiles (103/51 bars) in lieu of pressure-grouted micropiles. The anchors, ranging from 3 to 22 strands, were used for earth retention through both soldier pile and lagging walls and existing slurry walls. These anchors were complicated based not only on their size and length, but also the need to drill some of them under the historic Studebaker building. The overall magnitude of the project with considerations to resource management and material lead times will be addressed, highlighting critical strengths provided by the Contractor to ensure project success. The scope of work discussed in this paper was executed under two separate competitive bid contracts. The first contract included the support of excavation work and the second contract included the foundation package. The support of excavation comprised of drilled soldier piles (performed by Case Foundation as a subcontractor to the JV), driven soldier piles, driven sheet piles, hollow bar tiebacks, multi-strand tieback anchors and micropile soldier piles. The foundation package consisted of drilled micropiles. Due to the large scope of work and critical schedule requirements of the project, the JV had to think outside the box and present value engineered alternates to expedite installation durations.
Citation

APA: Di Stasim Jeffrey Frank Di Salvo Justin Lukens  (2019)  Efficient Deep Foundations, Earth Retention Systems and Ground Improvement – New School Techniques for Columbia Manhattanville’s Subsurface Challenges

MLA: Di Stasim Jeffrey Frank Di Salvo Justin Lukens Efficient Deep Foundations, Earth Retention Systems and Ground Improvement – New School Techniques for Columbia Manhattanville’s Subsurface Challenges. Deep Foundations Institute, 2019.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account