Abstract
Electronic detonators allow for variability and accuracy with blast delay selection and timing sequence. However, a single published guideline for selection of electronic timing delays is not available on the OneMine database. There are published documents that present options for timing with electronic detonators, some of which provide great detail and scientific evidence, but there is no single document that presents several different approaches with simple instructions on how to apply the various timing approaches.
This paper reviews published electronic timing approaches and results, then presents guidelines for electronic timing for alternative mining methods, which include: bench blasting (ie. quarries) and crater blasting (ie. metals mines). Most of the approaches are based on calculating milliseconds per meter for rock types, as quantified by the rock sonic velocity.
Guideline calculations are provided for recommended hole-to-hole delays and row-to-row delays for both free-faced bench blasting and crater blasting approaches. These are the two most common blasting methods for mining operations. Typically, free-faced bench blasting is the approach used in quarries with a bench height to burden ratio of around 4, and crater blasting is typically used in large blasthole diameter/short bench blasting in metals mines with a bench height to burden ratio of around 1.
Mines may focus on fragmentation, mucking rates, ore movement distance and movement direction. Recommendations are also included to provide general recommendations based on a mine’s preference for movement and fragmentation.
References include twelve studies on bench blasting and six studies on crater blasting. In addition, a discussion is included on the application of these recommendations at a full-scale surface gold mine.