Evolution and technical considerations to manage tailings at the RPP- 140 mining title (Antioquia - Colombia)

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 7
- File Size:
- 2574 KB
- Publication Date:
- Jun 17, 2024
Abstract
In Colombia, northeast of Antioquia, there is a gold deposit that has produced continuously since the
middle of the XIX century, located within mining title RPP-140, property of Gran Colombia Gold
Segovia (GCGS) since 2010. Mining materials are taken to the “María Dama” Processing Plant
where 1500 tonnes of materials are processed daily.
Before 2010, the previous owner of the mining title processed about 600 tpd and directly discharged
almost all tailings, given that they had no capacity to put them into final deposits.
El Chocho was conceived as a final tailings deposit to store the pulp produced by the processing
plant; it was divided into two phases with two dams (upper dam and lower dam) given that the
presence of illegal miners at the lower phase impeded a single dam design.
A squatter impeded construction of the upper dam; so afterwards, starting at the higher end was
necessary (owned by GCGS), building dam 1B to store tailings in pulp; after the squatter returned
the lands to the owner (GCGS), construction of tailings dam 1A was required and thus complete
construction of dam 1C or the upper dam.
While all of this was happening, GCGS decided to acquire a 1500 tpd filter press which currently
dehydrates tailings in order to take them to the valley controlled by dam 1A. Construction of dam 1A
was designed following the containment wall model, made with geotextile tubes.
These improvements generated reduced pressure on renewable natural resources because water
is recirculated and less fresh water contributions are required; less pressure is placed on soil, flora
and fauna because the area intervened for tailings storage will have a higher storage capacity and,
as such, a longer useful life.