Execution of Pile Installation in Environmentally Challenging Sites

Deep Foundations Institute
Emre Biringen Dena Morgan
Organization:
Deep Foundations Institute
Pages:
8
File Size:
933 KB
Publication Date:
Jan 1, 2014

Abstract

"Abstract This paper discusses the execution of pile installation and design issues at two environmentally challenging industrial sites in North America. Environmental regulations set constraints on the design and require versatility in choice of technology.For a proposed bridge, due to protected fish habitat, performing soil borings within 30 m of the creek embankment was prohibited. The limited subsurface profile indicated a thick upper layer of granular material, thus driving H-piles was considered. However, to limit generation of vibration and noise in the protected area, drilled piles had to be used. During execution, the subsurface profile differed from that in the borings 30 m away. Very soft, saturated silt was encountered at the bottom of the caisson and the length had to be redesigned very quickly while the contractor waited for instruction. For a new structure in uncontrolled fill area, performing soil borings was not allowed. It was known that a layer of peat was present in the area, but no information regarding the thickness and extent. The subsurface profile generally consisted of granular material overlying a thick compressible silt layer. Somewhere within the granular layer peat would likely be encountered. Franki piles were chosen to penetrate the peat and bear in the underlying granular material. During environmental sampling in the area, methane gas was encountered and Franki piles were no longer a viable option due to safety concerns. The foundation system was changed to steel H-piles driven to bedrock, which was more than 50 m below the ground surface and sloping. Rock shoes that would work to significant slopes had to be used in order to increase the likelihood of good embedment within the bedrock. Also, due to obstruction of an approximately 3 m thick debris field that was encountered in the upper granular soils, some of the piles had to be relocated and extra piling needed to compensate for such differences. The results of PDA testing to estimate compressive capacity and a series of lateral load tests are presented.INTRODUCTIONThe design issues that are encountered during construction can be quite problematic and have a significant impact on schedule. In order to avoid such impact on the project, a thorough subsurface investigation should be considered prior to design and construction. Better understanding of environmental regulations also prevents costly changes to the foundation design. This paper discusses the execution of pile installation and the design issues at two environmentally challenging sites in North America.BRIDGEDuring the subsurface investigation for a proposed industrial building complex, several boreholes were drilled within the footprint or in close proximity of various structures, with Standard Penetration (SPT) sampling of the upper coarse-grained soils (sand/gravel) and undisturbed sampling of the lower fine-grained soils (silt/clay). The SPT blow counts (N60) were corrected by a factor of 1.35 in order to incorporate the SPT automatic energy transfer ratio. When Modified California Sampler was used, a correction factor of 0.44 to 0.64 was also applied. N60 values were further corrected for gravel to avoid artificially high blow counts during the analyses due to spoon samples contact with gravel and cobbles, and the corrected values of (NG)60 (limited to a maximum value of 50 blows/300 mm) were used for design. The information from the SPT boreholes was then used to assess the subsurface conditions beneath the structures, as well as for a nearby bridge that was designed to cross over a creek. Since performing soil borings within 30 m of the creek embankment was prohibited due to the protected fish habitat, the investigation with regard to the bridge abutments was limited to two deep boreholes (B10-33 and B10-34) at the bridge location and two additional boreholes (B10-35 and B10- 36) located approximately 200 m upstream. The bridge location and two sets of boreholes are"
Citation

APA: Emre Biringen Dena Morgan  (2014)  Execution of Pile Installation in Environmentally Challenging Sites

MLA: Emre Biringen Dena Morgan Execution of Pile Installation in Environmentally Challenging Sites. Deep Foundations Institute, 2014.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account