Final Pit Wall Stability ù Understanding Crest Loss Mechanisms and Possible Solutions to Block Movement

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 6
- File Size:
- 1961 KB
- Publication Date:
- Jan 1, 2004
Abstract
This paper discusses the development of a strategy for ensuring long-term geotechnical stability of final pit walls at AngloGold AustraliaÆs Sunrise Dam Gold Mine. The strategy makes use of improved blasting techniques, changes to the mining sequence and other geotechnical techniques. Only the blasting techniques will be discussed in this paper. These were developed from numerous trials over a period of several months from May 2003 through to November 2003. The focus was to reduce crest loss damage and thereby improve final wall integrity, maintain designed safe berm widths, and ensure long-term stability. Crest loss mechanisms are now understood and are explained in this paper. The preferred solution is outlined; which is a combination of improved blasting and changes in the mining sequence to cater for pre-existing ground conditions. These ground conditions include dynamic hyper saline water with sometimes intersecting steeply dipping discrete structures. Project requirements were defined as mitigating or eliminating crest loss using 127 mm diameter pre-splitting and targeting minimal production blasting vibration levels against the walls. Blast results were measured by post blast visual inspections and video. Blast design input utilised the predictive algorithms built into simulation software when attempting to minimise vibration levels against the walls. Protection of the already fired pre-split line is now achieved using small charges against the wall and timing sequences which form a mask for the later firing main charges. The pre-split spacing is now modified to suit the geology. There eight blast domains identified around the perimeter of the pit, each having varying joint orientation. In addition, blasting the bench adjacent to the berm crest has particular considerations not required by the middle and lower benches. The preferred solution was to purposefully translate this damaged top section of the pre-split bench into a planned subsequent dig zone. The design of this top æweightÆ is a direct response to the nature of the crest loss mechanism.
Citation
APA:
(2004) Final Pit Wall Stability ù Understanding Crest Loss Mechanisms and Possible Solutions to Block MovementMLA: Final Pit Wall Stability ù Understanding Crest Loss Mechanisms and Possible Solutions to Block Movement. The Australasian Institute of Mining and Metallurgy, 2004.