Full Face Blasting in a Frozen Shaft

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 9
- File Size:
- 1040 KB
- Publication Date:
- Jan 1, 2019
Abstract
"This presentation will provide information and facts on the drilling and blasting within a frozen shaft using a full face methodology. The Author will briefly discuss the history of the sinking of a frozen shaft in Saskatchewan, the challenges faced, and the solutions delivered. The case study will include a discussion describing the series of events that led to the decision to adopt a full face blasting methodology. The case study will describe key elements such as the drilling pattern, hole size and depth, explosive products and blast vibration monitoring systems. INTRODUCTION During the shaft sinking process at a project in Saskatchewan, it was recommended that a drill & blast benching method be utilized. Following an evaluation of the site, the geological conditions proved amenable to a ground freezing system that would stabilize the rock formations and prevent inflows of water into the shaft (Table 1).The shaft sinking process required that the ground surrounding the proposed shaft be frozen by drilling several near vertical freeze holes radially at a specified distance from the edge of the proposed shaft excavation. This would allow for the circulation of a chilled brine solution down the freeze holes. The circulation is achieved by means of stainless steel pipes encased within each other to provide a delivery and return conduit for the brine (Figure 1). As a result of this periphery freezing, the ground within the shaft excavation is also predominately frozen.The finished internal diameter of the shaft was 5.5 meters with varying overall excavation diameters to facilitate different liner designs used for various rock formations. For the most part, the fully unsupported/unfinished excavated diameter of the shaft varied from 6.9 meters to 8.5 meters depending on the zone excavated. The challenge was that the proposed drill and blast excavation method posed a significant risk due to the potential to damage the freeze wall and pipes during blasting. The decision was made to commence the excavation through mechanical excavation (i.e. chip and cut) methods then change to a drill and blast method utilizing a split benching design. Through this process, the team encountered five main challenges: 1. Sub-horizontal geological structures and slips that affected blasting performance and sometimes resulted in a sloping surface to the top of the bench; 2. Confined working area for the crews and equipment due to a limited work area as a result of utilizing the split (half) bench drill and blast methodology; 3. Mechanical chipping and cutting of the one-meter buffer zone to the final shaft diameter; 4. Crews working on extremely slippery uneven frozen rock and ice surfaces, which affected safety and efficiency; 5. Establishing a blast vibration monitoring system to determine if the drilling and blasting of the full shaft excavation diameter were acceptable."
Citation
APA:
(2019) Full Face Blasting in a Frozen ShaftMLA: Full Face Blasting in a Frozen Shaft. Canadian Institute of Mining, Metallurgy and Petroleum, 2019.