Grouting of an Artesian Zone in Advance of Powerhouse Excavation for the Red Rock Hydroelectric Project

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 1637 KB
- Publication Date:
- Jan 1, 2016
Abstract
"The powerhouse for the Red Rock Hydroelectric Project is being constructed at the toe of the existing U.S. Army Corps of Engineers’ Red Rock Dam immediately adjacent to the existing stilling basin retaining wall. The powerhouse excavation extends though overburden and 40 feet into rock. Prior to rock excavation, a grouting was performed around the excavation for the purpose of increasing the strength of zones of fractured rock. For the majority of the perimeter, the rock was fairly tight and grout takes were relatively low. However, for a 160 foot extent along the landside of the excavation, extensive grouting was required to treat a two to five foot thick zone characterized by artesian flows from grout holes on the order of 20 gallons per minute (gpm) or higher from a voided zone in rock that was partially filled with sand, clay, and rock fragments. This paper discusses the treatment measures used to fill and improve the strength of this zone, which ultimately entailed a combination of thick cement grout and polyurethane grout, holes spaced as close as 18 inches on-center, and two additional rows of grout holes.IntroductionThe Red Rock Hydroelectric Project (Project) is currently under construction at the existing U.S. Army Corps of Engineers’ (USACE) Red Rock Dam on the Des Moines River near Pella, Iowa. At peak generation, the Project will generate up to 55 MW with an average annual energy output of 178 gigawatt-hours.The powerhouse for the Project will be located at the toe of the existing dam immediately adjacent to the existing stilling basin retaining wall. The powerhouse excavation extends up to a depth of 40 feet into rock through the St. Louis Limestone and terminates in the Warsaw Limestone. Prior to rock excavation, grouting was performed around the excavation for the purpose of improving the strength of zones of fractured rock. An auxiliary benefit of the grouting was reducing seepage into the excavation. Grouting began on July 20, 2015 and ultimately concluded on September 26, 2015.Drilling and grouting occurred as planned on the riverside (southwest) of the excavation along the cellular cofferdam and stilling basin wall (grout holes P-1 through S-13) and on the upstream (northwest) side of the excavation along the secant pile excavation support wall (grout holes P-14 through S-19) (refer to Fig. 1). The rock in these areas was generally tight with relatively low grout takes. However, on the landside (northeast) of the excavation (grout holes P-20 through P-28), partially infilled voids and artesian flows were encountered during drilling generally between depths of about 28 to 40 feet."
Citation
APA:
(2016) Grouting of an Artesian Zone in Advance of Powerhouse Excavation for the Red Rock Hydroelectric ProjectMLA: Grouting of an Artesian Zone in Advance of Powerhouse Excavation for the Red Rock Hydroelectric Project. Deep Foundations Institute, 2016.