Helical Pile Foundations at Tangier Island Substation

- Organization:
- Deep Foundations Institute
- Pages:
- 3
- File Size:
- 2088 KB
- Publication Date:
- Jan 1, 2017
Abstract
"A&N Electrical Cooperative provides electrical service to the counties of Accomack and Northampton along Virginia’s Eastern Shore and to Smith Island in Somerset County, Md.A&N recently worked to improve the efficiency of power distribution to a small island community and marina on Tangier Island in the Chesapeake Bay. This improvement consisted of upgrading the existing distribution substation with a new 25 kV 2-bay box distribution structure. Earth Contact Products (ECP) collaborated with PowerServices, Inc. (PSI) to design and install a helical foundation support system as part of the substation upgrade. Feasibility EvaluationThroughout the design process, A&Nworked with its partners PSI (design) andT&D Solutions (installation) to identifycost-effective alternatives. Foundationsystems considered included cast-in-placereinforced concrete caissons, precastconcrete foundations, driven steel piles and helical piles. In evaluating all of theoptions, the greatest concern was gettingthe material onto the island, followedclosely by the availability of the equipmentto install the foundations. Clearly, cost,more specifically the installed cost, was asignificant consideration and decisionfactor throughout the process.There were several limiting factors that had to be considered during the design process, the most significant of which was that all of the material had to be barged to the site. With traditional reinforced concrete deep foundations in mind, the cost for installing these piles was projected to be nearly $2,000/cu yd ($262/cu m) of installed concrete. Given that approximately 5 to 6 cu yd (3.8 to 4.6 cu m) of concrete would be required for this structure, the cost was significantly high for this project. What’s more, because the components of the concrete mix would have to be barged and then hand mixed on site, there was concern regarding both the time required to complete the piles and the quality of the installed concrete. For the driven pile alternative, the availability, or lack thereof, of equipment and material cost resulted in a total cost estimate that was more expensive than that of the concrete piling alternative. The high material cost for the piles, which was more than double than the cost of concrete, was due to the number and size of piles needed to resist the overturning moment. Ultimately, the team selected the helical pile alternative. The decision to a use helical pile foundation system was based on many factors, not the least of which was the remote location of the project site and the difficulties associated with getting material, equipment and construction personnel to the project site."
Citation
APA:
(2017) Helical Pile Foundations at Tangier Island SubstationMLA: Helical Pile Foundations at Tangier Island Substation. Deep Foundations Institute, 2017.