High-Capacity Hoisting at Rondout West Branch Tunnel Project

Society for Mining, Metallurgy & Exploration
Donald Brennan Derek Brennan
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
9
File Size:
6818 KB
Publication Date:
Mar 1, 2019

Abstract

"The existing Rondout West Branch Tunnel (RWBT) is part of the Delaware Aqueduct which has been in service since 1944 and accounts for more than 50 percent of New York City’s water supply. In early 2015, the New York City Department of Environmental Protection contracted Kiewit-Shea Constructors, AJV (KSC) to construct the Rondout West Branch Bypass Tunnel project (Rondout) in order to mitigate the leakage of 132 million L/ day (35 million gpd) of water from two areas of the existing tunnel; the Roseton and Wawarsing areas.The scope of the Bypass Tunnel 2 project is separated into two distinct phases. Phase 1 consists of completing the shaft sinking to a depth of approximately 274 m (900 ft) at shaft 5B, 213 m (700 ft) at shaft 6B and the excavation of approximately 3,850 m (12,500 linear ft) of tunnel at a diameter of 6.6 m (21 ft 7 in). This phase also includes the installation of 2,804 m (9,200 linear ft) of 4.8 m (16 ft) diameter steel interliner pipe through the new bypass tunnel with cast-in–place concrete liner for a finished diameter of 4.2 m (14 ft). Access chambers at the top of shafts 5B and 6B will be constructed for access and housing of the mechanical and electrical equipment for supporting pumps and valves.Included in phase 2 is the additional excavation from shafts 5B and 6B to the RWBT, and the drainage tunnel to remove ground water infiltration from RWBT. This work will be completed during a scheduled shutdown of the RWBT and will include approximately 31 m (100 ft) of excavation of the two connection tunnels. Additionally, construction of the permanent plugs within the RWBT will be undertaken. Figure 2 shows the layout of the work.Access to the work through the deep shaft at site 5B was critical to the success of the project. The hoisting system needed to be multi-functional to handle the different types of construction from drill and shoot of the shaft, starter and tail tunnel, the assembly of the tunnel boring machine (TBM), the excavation of the TBM tunnel including the supply of the precast segmental liner, the grouting operations, the installation of the steel interliner pipe and the cast-in-place concrete as well as ingress and egress of personnel. The production of the TBM operations was critical to the schedule of the project. This required a quick cycle for muck haulage and supply of the precast segmental liner in order to keep pace with the excavation time of the TBM. For TBM assembly, components were limited to a maximum weight of 104 t (115 st) for a single lift. Various cranes were analyzed for hoisting, however, none would meet all of the citeria. Therefore, the project team selected a specialized hoisting system designed in house in conjunction with Timberland Equipment Ltd. that consisted of a total of 14 separate hoists and winches with a total of more than 2,833 kW (3,800 hp)."
Citation

APA: Donald Brennan Derek Brennan  (2019)  High-Capacity Hoisting at Rondout West Branch Tunnel Project

MLA: Donald Brennan Derek Brennan High-Capacity Hoisting at Rondout West Branch Tunnel Project. Society for Mining, Metallurgy & Exploration, 2019.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account