Horseshoe Secant Compression Shoring System For Tunnel Repair

Deep Foundations Institute
Rob Jameson Noah Maier Giuseppe Gaspari Karen Talbot
Organization:
Deep Foundations Institute
Pages:
11
File Size:
1950 KB
Publication Date:
Oct 1, 2022

Abstract

A storage and drainage tunnel advancing below I-75 in Detroit, Michigan experienced sudden subsidence. The Tunnel Boring Machine (TBM) was damaged to the extent that its shield, cutting head and extensive interior components needed to be extracted and replaced along with several completed tunnel segments. The tunnel was 16 feet (4.9m) in diameter with crown over 79 feet (24m) deep at the time. The tunneling contractor immediately engaged their designers and specialty subcontractors to develop a scheme to access the machine and repair the tunnel. They required a shaft 99 feet (30m) deep, with unobstructed plan dimension of 50 feet (15m) to accommodate the large components that needed to be removed and replaced. This precluded the application of an internally braced excavation and instead earth support solutions focused on use of a compression ring. Since the completed tunnel section behind the TBM obstructed closure of the compression ring below its invert, this paper describes the innovative access shaft solution employed. A conventional compression ring was constructed using 5 feet (1.5m) diameter drilled shafts down to the tunnel crown. In front of, and to the sides of the tunnel heading, the secant shafts were extended to over 150 feet (46m) depth, creating a horseshoe of support extending 50 feet (15m) below the planned excavation invert. Larger diameter "King Pile" shafts were drilled immediately to either side of the tunnel, overlapped into each end of the secant "horseshoe". The king pile shafts, together with a heavily reinforced ring beam above the crown elevation, acted as a door frame to transfer hoop loads from the incomplete secant arc into reaction supports above and below the tunnel. These oversize king pile shafts were extended and socketed into rock over 70 feet (21m) below tunnel invert. Very tight installation tolerances were necessary to maintain secant shaft alignment to depths exceeding 150 feet (46m). The project operational, geotechnical, and quality data was managed and visualized using a custom GIS interface. This paper will present the design approach employed and review the construction and quality program selected to repair the tunnel.
Citation

APA: Rob Jameson Noah Maier Giuseppe Gaspari Karen Talbot  (2022)  Horseshoe Secant Compression Shoring System For Tunnel Repair

MLA: Rob Jameson Noah Maier Giuseppe Gaspari Karen Talbot Horseshoe Secant Compression Shoring System For Tunnel Repair. Deep Foundations Institute, 2022.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account