Hydrocutter-Excavated Slurry Wall for Center Hill Dam Foundation Remediation

Deep Foundations Institute
Michael Arnold Bob Faulhaber Joe Nichols
Organization:
Deep Foundations Institute
Pages:
9
File Size:
1289 KB
Publication Date:
Jan 1, 2017

Abstract

"Center Hill Dam is a critical part of the infrastructure controlling floods at the Caney Fork River and reducing flood levels at the Cumberland, lower Ohio and Mississippi Rivers. The Center Hill Dam Foundation Remediation Project was necessary to address Karst features in the foundation rocks and observed signs of distress of the dam. From 2011 to 2014 BAUER Foundation Corp. (BFC) performed deep foundation works for this project. The executed features of work include the installation of two walls. The first wall extends throughout the clay embankment into the underlying rock to provide encasement during the construction of the second wall. Its width of 7.4 feet makes it the widest diaphragm wall ever installed. The second wall is the actual seepage barrier and provides a continuous 2- feet wide wall. It extends through the first wall into the underlying rock and is up to 300 feet deep. The paper introduces the project, the requirements specified by United States Army Corps of Engineers (USACE) for encasement and barrier wall and the approaches taken by BFC. It discusses the ground conditions and describes the excavation equipment as well as the excavation methods used. A special focus is put on the steering capabilities of the hydrocutter equipment and the verticality performance.PROJECTBeginning in 2011, BFC was tasked by the USACE with the installation of a seepage barrier/cutoff wall at the Center Hill Dam Foundation Remediation project under a partially performance based specification. The remediation was necessary due to karst features in the foundation rocks and observed signs of distress, which led USACE to rate the dam with the most critical dam safety action classification (DSAC I). The executed features of work include the installation of two walls. The first wall, an encasement wall, extends vertically through the clay embankment and is embedded minimally into the underlying bedrock to provide embankment stability during the construction of the second wall, the barrier wall. The encasement wall is constructed of overlapping panels 7.4 feet (2.25 m) wide, which is the widest diaphragm wall ever installed, and up to 210 feet (64 m) deep. The second wall is the seepage barrier and provides a continuous 2 feet (0.6 m) wide wall consisting of overlapping panels. It extends through the encasement wall into the underlying bedrock and is up to 307 feet (93 m) deep. BAUER BC40 and BC50 hydrocutters mounted on MC96 and MC128 foundation cranes were used to perform the majority of the works (Figure 1). Excavations were performed under bentonite slurry (encasement wall) and water (barrier wall) and concrete was poured with the tremie method. Adding to the challenges, the project had to be executed in an environmentally sensitive area. Based on the high risk, a special focus was put on monitoring, quality control and geometric accuracy. The WallTracker information management system was used to share all relevant data between BFC and USACE (Roff et al. 2014)."
Citation

APA: Michael Arnold Bob Faulhaber Joe Nichols  (2017)  Hydrocutter-Excavated Slurry Wall for Center Hill Dam Foundation Remediation

MLA: Michael Arnold Bob Faulhaber Joe Nichols Hydrocutter-Excavated Slurry Wall for Center Hill Dam Foundation Remediation. Deep Foundations Institute, 2017.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account