Innovative Riverbank Erosion Control Retaining Wall System for the Brazos River

Deep Foundations Institute
Will Bohlen Tracy Brettmann
Organization:
Deep Foundations Institute
Pages:
10
File Size:
1817 KB
Publication Date:
Jan 1, 2018

Abstract

An innovative retaining wall design consisting of tangent drilled shafts with supplementary seal piles was used to limit continuing bank erosion along the Brazos River in Southeast Texas. The riverbank erosion had progressed to where it was threatening the stability of both the bridge abutment and corresponding approach embankment of the heavily travelled Highway 99 bridge at this location. A tangent pile design was selected because it was both much faster to install and more cost effective than a secant pile system. The design included both 5.5-ft and 10-ft diameter shafts with depths up to 130-ft and comprised both anchored and cantilevered sections. Supplementary seal shafts were also installed between the structural tangent drilled shafts to help plug any gaps between the tangent shafts. The plumbness and diameter of the shafts were tested using a sonic caliper to make sure the shafts were installed within the specified tolerance. The initial design had to be revised when a record flood from Hurricane Harvey impacted the site during construction. Introduction The Fort Bend Grand Parkway Toll Road Authority (Owner) needed to protect the north bridge abutment with a retaining wall system due to rapidly eroding conditions of the Brazos River banks within the 300- feet-right-of-way of the State Highway 99 Jodie Stavinoha Bridge. The extent of the local scour and erosion along the north bank of the Brazos River has caused concern for the structural integrity of the bridge. The magnitude of the erosion along the north bank at the location of the bridge has been measured at about 120 feet over three recent hydrologic flood events locally referred to as Memorial Day 2015, Memorial Day 2016, and Tax Day 2016. During construction, a new record flood level occurred due to Hurricane Harvey in August of 2017 that resulted in a portion of the retaining wall needing to be redesigned due to even more erosion occurring. The Brazos River is an actively eroding and meandering alluvial river plain that naturally meanders and migrates over time. The processes of bank erosion and meander migration were ongoing before the bridge was constructed and will continue in the future. These recurring major flood events, however, rapidly increased the rate of erosion in just a few years. Background. Due to the need to protect the bridge as soon as possible, the Owner selected a project team consisting of the designer, general contractor and specialty deep foundation contractor prior to final design to work together in developing a cost-effective design that could be implemented rapidly. The project team initially considered both a secant pile and tangent pile retaining wall system using drilled shafts. After reviewing various alternative designs, a tangent pile wall with seal piles was selected based on both cost effectiveness and speed of installation. The tangent pile with seal pile option was approximately 20 percent lower in cost and 50 percent faster to install.
Citation

APA: Will Bohlen Tracy Brettmann  (2018)  Innovative Riverbank Erosion Control Retaining Wall System for the Brazos River

MLA: Will Bohlen Tracy Brettmann Innovative Riverbank Erosion Control Retaining Wall System for the Brazos River. Deep Foundations Institute, 2018.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account