Lessons Learned From Construction Of A Tire Plant In Karst, Ns2 Tires, White, Ga

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 1304 KB
- Publication Date:
Abstract
This case history for three major additions to a tire manufacturing plant in north Georgia discusses the
impact of highly variable Karst (sinkhole) geology on both foundation design and construction. For Phase
3, alternatives were considered for a heavily loaded mixing tower with up to 2,000 kip column loads. A
non-traditional approach of using auger cast piles was adopted. To satisfy a risk-averse Owner, a pile load
testing program including strain gauges was conducted. One test pile was cored full depth to demonstrate
effective bearing on steeply inclined rock. For Phase 4, similar methodology was used at another critical
mixing tower structure associated with that phase and the installation procedure was refined to reduce
grout take. In Phase 5 construction, another mixing tower and the equipment pits were supported on auger
cast piles. After pile installation, a sinkhole opened up between two equipment pits. Remedial grouting
was performed. Development also required construction of a R&D building over a 96 inch diameter RCP
storm sewer. Auger cast piles were used to support the building to avoid overstressing the existing pipe
and risk separating joints. This case history outlines lessons learned while constructing auger cast piles in
Karst and proving quality was built into the foundations.
Citation
APA:
Lessons Learned From Construction Of A Tire Plant In Karst, Ns2 Tires, White, GaMLA: Lessons Learned From Construction Of A Tire Plant In Karst, Ns2 Tires, White, Ga. Deep Foundations Institute,