Levee Repair and Upgrade by Dual Sheet Pile Walls and Accordion Sheet Pile Wall

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 2848 KB
- Publication Date:
- Jan 1, 2017
Abstract
"This paper discusses the unique design and construction circumstances of the cantilevered dual sheet pile walls and the Accordion Sheet Pile Wall for the repair and upgrade of the East Garden Grove-Wintersburg Channel in Huntington Beach, California that was concluded in 2014. It also describes the 2008 Emergency Sheet Pile Project for the same channel. Both projects utilized the Press-in Piling Method for its low noise and almost no vibration advantages.BackgroundThe East Garden Grove-Wintersburg Channel is part of the Orange County Flood Control District (OCFCD) and is operated and maintained by OC (Orange County) Public Works (see Figure 1 for its location). The channel, referred to as OCFCD facility # C05 (C05), had suffered significant toe undercutting and slope erosion of its levee due to a series of storms. These began after the facility was constructed in the 1960’s and culminated in 2005. Consequently, the levee was deemed significantly deficient and was eventually declared as a local emergency in 2007. C05 was an incised channel and its levee was constructed primarily from native materials. Operation and Maintenance (O&M) personnel notified the design staff at OC Public Works to be aware of major consequences associated with the dilapidation problem in the most downstream reach of the channel in the vicinity of the Bolsa Chica Wetlands Restoration Project. In 2007, the Orange County Board of Supervisors declared a local emergency to fix the levees with sheet piles to be driven by the Press-in Piling Method, hydraulic pushing piles into ground by holding onto previously installed piles. The project that ensued represented the first in-tandem use on the West Coast of the United States of the Press-in pile driver with its GRB System (Press-in pile driver, a support crane and pile transporter travel on top of already-driven sheet piles). This is further discussed in this paper in the sections titled “Press-in Piling Method” and “GRB System”, respectively. The project repaired approximately 3,800 feet of erosion on the north levee of C05 with 45-foot long cantilevered sheet piles. The sheet piles design constraints are discussed in this paper in the section titled “C05 2008 Emergency Sheet Pile Project (Phase 1)”. Between 2012 and 2014, another mile’s worth of levee reach was improved with the Soil-Mix-Sandwich (SMS) Method. This concept consisted of deep soil cement mix (DSCM) columns sandwiched within the dual rows of sheet piles. Additional details on the SMS, its DSCM construction, and its hybrid geo-structure design concepts are well beyond the scope of this discussion, which is primarily focused on sheet piles. Instead, the interested reader is referred to two papers on the SMS and its DSCM metrics (Fayad, 2015; and Arora, et al., 2015). These were presented and published in the Proceedings of the Deep Foundations Institute (DFI) 2015 Conference on Deep Mixing. Hence, in the section of this paper titled “C05 SMS Dual Sheet Piles Project (Phase 2)” only the sheet pile design constraints of the SMS are covered. Finally, in the area where the project traversed the Alquist-Priolo zone of the Newport-Inglewood tectonic fault, an expandable and deflectable sheet pile wall was used to isolate the flood channel from the Bolsa Chica wetlands. Its details are addressed in the section titled “C05 Accordion Sheet Pile Wall (Phase 2)” of this paper."
Citation
APA:
(2017) Levee Repair and Upgrade by Dual Sheet Pile Walls and Accordion Sheet Pile WallMLA: Levee Repair and Upgrade by Dual Sheet Pile Walls and Accordion Sheet Pile Wall. Deep Foundations Institute, 2017.