Lucky Friday’s No. 4 Shaft - Ten Years from Concept to Completion

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 11
- File Size:
- 1497 KB
- Publication Date:
- Jan 1, 2019
Abstract
"Hecla Limited’s No. 4 Shaft at the Lucky Friday Mine is the largest capital expenditure in the corporation’s 128-year history and is considered the deepest shaft in the United States. This paper will discuss the project’s history and lessons learned from the initial conceptual design work in 2007 through project commissioning in 2017. Change management was key for the owner, contractors, and vendors in delivering the operational and organizational success on the project. The No. 4 Shaft has extended the life of the Lucky Friday Mine by 21 years to 2039. INTRODUCTION The Lucky Friday Mine of Hecla Mining Company (Figure 1) is the oldest active (77 years) and deepest mine in the Coeur d’Alene mining district, producing approximately 725 tonnes (800 tons) per day from narrow, vertical, silver, lead, and zinc veins. Primary access into the mine is via the Silver Shaft, a 5.5-m (18-ft) diameter, concrete lined shaft sunk to an original depth of 1,890-m (6,200-ft). Current production is from the Gold Hunter vein system, approximately 1,525-m (5,000-ft) northwest of the Silver Shaft.Cut and fill stoping is currently employed at depths to 2.3 km (7,500 ft) below ground surface, making it one of the deepest mines in the western hemisphere. No. 4 Shaft is a 5.5-metre (18-foot) diameter, concrete lined circular shaft, constructed as a 1.2 km (3,860 feet) deep winze in the Lucky Friday Mine. The 2.4 m (8 ft.) diameter, double drum, double clutch, Siemag hoist and associated headworks are situated at the 4760 level, top station at 4940 and shaft stations at 5900, 6500, 6580, 7500, 7580, 8300, 8380, 8500, and 8620. Shaft stations reference depth below Silver Shaft top station. The 4 Shaft was designed, constructed and commissioned over ten years, between 2007 and 2017. Basic design work was completed by Nordmin Engineering, followed by detailed design completed by Cementation Canada. Shaft construction was awarded to Cementation USA and lateral development was initiated in early 2008. Over the course of the next nine years, the project was suspended and restarted twice, dealt with the loss of a miner, added scope including shaft depth and mine infrastructure facilities, experienced squeezing ground that required liner replacement, changed excavation section, and dealt with a final alignment that was not within design requirement for verticality. Hecla and Cementation were successful in delivering a facility that provides fully functional access from collar at 4940 level to shaft bottom at the 8620 level. Two active mining levels below the collar, 5900 and 6500 are accessed. In addition, the shaft provides access to the future mining level at 7500, skip loading facility at 7580 level, station and loading pocket cutouts at 8300 and 8380 levels, spill pocket at 8500 level, and shaft bottom pumping facility at 8620 level (Figure 2)."
Citation
APA:
(2019) Lucky Friday’s No. 4 Shaft - Ten Years from Concept to CompletionMLA: Lucky Friday’s No. 4 Shaft - Ten Years from Concept to Completion. Canadian Institute of Mining, Metallurgy and Petroleum, 2019.