Observed Driving Performance of Open-Ended Steel Pipe Piles with and Without Plugged Toes

- Organization:
- Deep Foundations Institute
- Pages:
- 12
- File Size:
- 2262 KB
- Publication Date:
- Jan 1, 2019
Abstract
This paper presents the performance of nineteen open-ended steel pipe piles driven through highly variable overburden soils into glacial till and schist bedrock. The piles were 16 inches in diameter and 0.656 inches thick, with yield strength of 50 ksi. The piles were designed for a service capacity of 250 kips and were driven to achieve an ultimate geotechnical capacity of at least 500 kips. Due to the large variation in the ground conditions, installed pile lengths ranged from 25 to 66 feet. Some piles were driven to refusal on the bedrock while others were terminated at final driving resistance of 2 to 7 blows/in. Two piles were suspected to be plugged during driving while others did not. Each pile was instrumented with strain gages and accelerometers near the pile top, and observed using a Pile Driving Analyzer (PDA) to provide preliminary guidance on pile capacity achieved at end of initial drive (EOID). The influence of plugged and unplugged pile toe conditions on the interpretation of pile capacity was investigated using Case Pile Wave Analysis Program (CAPWAP). Characteristics of driving energy, compressive and tensile stresses developed in the steel pipe piles, and the resulting pile deformation behavior are discussed.
INTRODUCTION
The Hunters Point South redevelopment in Long Island City, Queens is one of New York City’s major efforts to transform former manufacturing zones into mixed developments for the middle-income community. The site is located along the eastern shoreline of the East River and Newtown Creek. The development included low to high-rise residential buildings, a public school and retail structures. Open spaces were created along the East River and Newtown Creek waterfronts in the form of a continuous park providing for recreational and community related activities. Waterfront structures included small park buildings, walkways and viewing platforms with the shoreline protected by revetments as part of the City’s flood mitigation strategy. The project was implemented in two phases, with completion of construction for Phase 1 in 2013 and Phase 2 in 2019.
Based on available historical information, extensive reclamation took place between 1855 and 1898. After 1951, changes to the shoreline were made along the East River, including the removal of reclaimed land along the northern portion of the project site to allow for docking facilities. By 1977, these facilities had been demolished and backfilled to form the current shoreline configuration. The present site was temporarily used as a parking lot with stockpiles of fill mixed with construction demolition rubble, rip-rap and boulders of varying heights across the site. The existing ground surface varied significantly up to approximately 25 feet difference in elevation. The stockpiles were removed and the site was re-graded during final development of the project. This paper discusses the foundation design challenges due to the loose overburden soils and potential obstructions within the fill material, in particular, the issues relating to installation of open-ended steel pipe piles through the ground conditions encountered on site.
Citation
APA:
(2019) Observed Driving Performance of Open-Ended Steel Pipe Piles with and Without Plugged ToesMLA: Observed Driving Performance of Open-Ended Steel Pipe Piles with and Without Plugged Toes. Deep Foundations Institute, 2019.