Observed Loading Behavior During Cross Passage Construction - Brisbane Airport Link Project

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 10
- File Size:
- 3667 KB
- Publication Date:
- Jan 1, 2016
Abstract
"INTRODUCTIONTwin bored tunnels are commonly used for a variety of road and tunnel projects throughout the world. A major component of these twin tunnel projects is the construction of connecting cross passages that provide emergency access between tunnels and space for tunnel service equipment. Cross passages can present significant geotechnical risk and technical challenges to a project – support systems must be considered for redistributing loads around the mainline tunnel openings and supporting new loading resulting from excavation activities. Additionally, cross passages pose risks to construction schedule and cost because of their sequencing at the end of construction, so mitigation of schedule overruns can be critical. By observing field instrumentation data records from completed projects, a betterunderstanding of the force development in each temporary structure can be achieved with indication of which structures are the most critical to support ground loads.This paper discusses the data obtained during the Brisbane Airport Link construction project, a road tunnel located in Brisbane, Australia. Strain gauge instrumentation data from the precast segmental lining and propped opening steel sets is presented with relation to the construction sequence and local geology. Interpretations and conclusions based on the observed trends are proposed, with several key mechanisms affecting the loading and unloading identified.Brisbane Airport Link Project OverviewThe Brisbane Airport Link project in Brisbane, Australia, connects central Brisbane to the airport located northeast of the downtown with over 7km of twin-bore road tunnels, two lanes each, with several caverns, interchanges, and access ramps constructed along the alignment to connect to other key routes in the city. The project was executed under a Public-Private Partnership (P3) scheme, funded and operated by the consortium BrisConnections. The main contractors were a joint venture of John Holland and Theiss, while the design was carried out by Arup and Parsons Brinckerhoff.Construction of the tunnels was conducted using a combination of 17 roadheaders and two 12.5m double-shield Herrenknecht TBMs [1]. The TBMs were used in EPB-type closed mode for the initial portion of their drive, starting at the northeast end of the alignment. Tunneling started in soft ground, weathered rock, and mixed face conditions initially, progressing to competent sedimentary rocks as the drive continued. Support was accomplished using a 12.1 m diameter steel fiber reinforced concrete (SFRC) segmental lining installed behind the TBMs in a 9 segments + 1 key arrangement. The innovative design of these segments is detailed in the paper by Harding and Francis [2]. Ancillary roads and underground interchange caverns were constructed by sequential excavation techniques using roadheaders, accounting for nearly half of the total underground excavations."
Citation
APA:
(2016) Observed Loading Behavior During Cross Passage Construction - Brisbane Airport Link ProjectMLA: Observed Loading Behavior During Cross Passage Construction - Brisbane Airport Link Project. Society for Mining, Metallurgy & Exploration, 2016.