Potash production hoisting plant upgrade and beyond

Society for Mining, Metallurgy & Exploration
D. M. Ziebarth
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
10
File Size:
23877 KB
Publication Date:
Apr 1, 2017

Abstract

"During the mid to late 1960s, the underground potash industry in Saskatchewan was born. For the next four decades the industry operated at a steady pace, supporting a large part of the world demand, until 2008 when the potash market heightened. Operators were motivated to capitalize on this increased demand, new mines were proposed while existing mines were planning upgrades. Potash Corp. of Saskatchewan (PCS) was one of the major producers planning upgrades to its production facilities quickly, including modifying the existing headframe and shaft at the PCS Cory Site to accommodate a new 1.5-kt/h (1,650-stph) hoisting plant. Upon completion of the project, the innovative operations group continuously reviewed methods to increase production and reduce operating costs, allowing PCS to continue being competitive on the world market.BackgroundPotash production is a major Saskatchewan industry and has played a significant role in the economy for more than 40 years. Production commenced in 1962 when water problems were overcome at the International Minerals and Chemical (IMC) Mine near Esterhazy, Saskatchewan. A surge of development by other companies resulted in 12 companies opening 10 mines by 1970. In 1975, Potash Corp. of Saskatchewan was created by the government of Saskatchewan, and shortly thereafter purchased several mines in Saskatchewan, including the Cory Mine, near Saskatoon.Cory has been in operation since 1968 and is located 12 km (7.5 miles) west of Saskatoon in central Saskatchewan. The mine is located in the center of the world’s largest potash deposit, 1,000 m (3,300 ft) below surface.PCS has embarked on sizable capital expansions of more than CDN$7 billion.The $1.6-billion Cory expansion was expected to raise operational capability of the site to 2.7 Mt/a (3 million stpy), an increase of 1.9 Mt/a (2.1 million stpy). To achieve 2.7 Mt/a (3 million stpy) of finished product and considering the 22.6 percent average production recovery (Potash Corp, 2013), 12 Mt/a (13.2 million stpy) of ore must be hoisted to the surface for processing. To deliver this rate required upgrading of the hoisting plant to 1.5 kt/h (1,650 stph). To accomplish this ambitious challenge, creative thinking, careful planning and a cohesive team was needed to work together to ensure the schedule, budget and most importantly that the work was completed safely (Potash Corp., 2013)."
Citation

APA: D. M. Ziebarth  (2017)  Potash production hoisting plant upgrade and beyond

MLA: D. M. Ziebarth Potash production hoisting plant upgrade and beyond. Society for Mining, Metallurgy & Exploration, 2017.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account