Rebuild of a Flash Smelting Furnace Using Explosives

- Organization:
- International Society of Explosives Engineers
- Pages:
- 12
- File Size:
- 4263 KB
- Publication Date:
- Jan 1, 2016
Abstract
"Kennecott Utah Copper (KUC) Smelter scheduled a rebuild of their flash smelting furnace forSeptember, 2014. KUC’s goal in this project was to reduce the rebuild time from 65 to 55 days by using explosives to break the matte and brick layers of the uptake shaft and hearth sections of the furnace. Previous rebuilds had employed the slower technique of mechanical breakers to remove the matte and brick layers which took 22 days. KUC has many years of experience in removing slag from the uptake shaft, but they had never used explosives to remove the hearth. As far as KUC was aware, no other smelter operation had attempted a hearth removal in this way."
Citation
APA:
(2016) Rebuild of a Flash Smelting Furnace Using ExplosivesMLA: Rebuild of a Flash Smelting Furnace Using Explosives. International Society of Explosives Engineers, 2016.