Rehabilitation of Underground Surge Bunker Following Massive Rib Wall Failure

International Conference on Ground Control in Mining
Rob Robinson
Organization:
International Conference on Ground Control in Mining
Pages:
9
File Size:
1229 KB
Publication Date:
Jan 1, 2007

Abstract

Following a massive rib wall failure along the reclaim belt of the large underground surge bunker at CONSOL?s Bailey Mine, a multifaceted, cleanup and rehabilitation effort was initiated to rapidly stabilize the bunker rib walls and place the bunker back into production. Rehabilitation of the bunker included infilling and re-mining of the failed excavation area, installing a system of horizontal tie-back cable bolts, constructing a large knee wall at the base of the rib, reducing water inflow, and providing drainage for rib water. As a result of the coordinated effort, the bunker was safely placed back into production within 38 days. The 7500-ton surge bunker, an engineering feat in itself, was constructed in 2003 to accommodate production surges from two longwalls. In 2005, 14.8 million raw tons passed through the bunker. The 22-foot wide by 75-foot high surge bunker excavation extends as much a 52 feet below the base of the Pittsburgh seam. The bunker excavation measures 325 feet in length, with feeder and reclaim belt excavations extending the bunker excavation by approximately 500 feet. The massive rib roll, which occurred near the bottom of the reclaim belt slope, measured as much as 45 feet high by 60 feet long. Failure of the rib was attributed to progressive failure of a thick claystone unit present near the slope bottom area. Saturation of the claystone by water inflow, high insitu horizontal stress, and pre-existing rock joints were considered contributing factors. Immediately after rib failure, mine production was temporarily rerouted to a parallel belt. Two bulkheads were then constructed 175 feet apart along the reclaim belt slope, and a customized fly ash-cement mixture was pumped from the surface into the unstable reclaim slope area. A tunnel was then mined through the backfill along the original reclaim slope contour; the new excavation supported by a system of customized steel sets. To assure stability of the adjacent bunker rib wall, a pattern of 70-foot long cable bolts were installed downward from the adjacent entries to effectively tie back the rib. Drainage holes and a 12-foot high knee wall were installed. Adjacent gas wells were also plugged to help reduce inflow. Periodic inspections and continuous monitoring are being used to help assure bunker stability.
Citation

APA: Rob Robinson  (2007)  Rehabilitation of Underground Surge Bunker Following Massive Rib Wall Failure

MLA: Rob Robinson Rehabilitation of Underground Surge Bunker Following Massive Rib Wall Failure. International Conference on Ground Control in Mining, 2007.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account