Abstract
"Longwall shearers are widely employed in underground coal mines. The reliability of such machine has significant importance for successful mining operations. This paper aims at studying reliability of a longwall shearer using failure data recorded for a year. Data was pre-processed, sorted and selected for analysis. Selected data is then examined using statistical models. Distribution fitting of time-between-failure (TBF) and time-to-repair (TTR) are accomplished using three different models. Goodness-of-fit criteria is used to ascertain the best fitting model. Reliability in terms of mean-time-between-failure (MTBF), and mean-time-to-repair (MTTR) are calculated using the model which best represents the failure data. Exponential distribution best represents the time between failure and lognormal distribution the time to repair data. A well-known risk management technique Failure Mode Effect and Criticality Analysis is used to evaluate the critical breakdowns. Critical system/parts, experiencing regular failures is delineated based on this analysis. INTRODUCTION Mining is a capital intensive process, and huge monetary investment is required to develop and operate a mining project. Heavy and expensive equipment’s are employed in development and operation of these projects. In order to ensure timely completion of set milestones, it is mandatory that equipment’s perform their required task productively. Delays are not unusual owing to breakdown of these equipment’s. Breakdown or failure experienced by any of the equipment pose heavy financial burden. Moreover, frequent times, companies have to employ and dedicate additional resources to make up for such delays. Delays in project is not only detrimental to company’s image in market, but it also interrupts customer commitments. Mines having history of not fulfilling their promise usually get lower commodity price. Penalties are also imposed on the companies defaulting its obligations. Especially, in today’s world where competition among the companies are growing, success means keeping up the commitments in a timely manner. Heavy machinery and equipment are instrumental in success of any project. These machinery and equipment’s have to reliable in a sense that they can perform the set task in given time period. Reliability of these equipment plays a pivotal role in success of any project. The reliability analysis of mining equipment has long history. Many researchers have applied different statistical models for analyzing the reliability of mining machines (Samanta, Sarkar [1]. Kumar and Klefsjö [2] demonstrated the use of the power law process model for reliability assessments of repairable mining machines. Barabady and Kumar [3] performed the reliability analysis from failure data of the crushing plants."
Citation
APA: (2018) Reliability Analysis of a Longwall Shearer Machine Using Statistical Methods: An Application
MLA: Reliability Analysis of a Longwall Shearer Machine Using Statistical Methods: An Application. Society for Mining, Metallurgy & Exploration, 2018.