Removal of the Former San Francisco-Oakland Bay Bridge Foundation Caisson E3 by Mechanical Means and Explosives

Deep Foundations Institute
Michael Gebman Jack Gerwick
Organization:
Deep Foundations Institute
Pages:
10
File Size:
1779 KB
Publication Date:
Jan 1, 2016

Abstract

"With the opening of the new San Francisco-Oakland Bay Bridge East Span, the former bridge and its caisson foundations are being demolished. Caisson foundations are in the path of a future shipping channel and therefore need removal down to the mudline 50 ft below water (MLLW). For the first caisson to be removed (E3) a mechanical demolition was performed above the waterline and an implosion was done for the remaining caisson down to mudline. Mechanical demolition consisted of excavators operating from either on top of the caisson, from work platforms or from barges. The demolition was implemented on a trial basis with a successful implosion on November 14, 2015. The work was conducted in an environmentally sensitive area, with measures taken to protect fish, marine mammals and birds. This demolition technique was cost effective, faster to execute, and had a better environmental impact then an alternative option. The demolition, measures implemented to protect the environment, outcome, and lessons learned are presented.INTRODUCTIONThe California Department of Transportation needed a cost effective and environmentally friendly solution for removal of the remaining San Francisco-Oakland Bay Bridge (former East Span) caisson foundations, starting with caisson E3. This was necessary to clear a future shipping channel. One option was to construct a steel cofferdam around the caisson to allow demolition in the dry down to the mudline. This option would take years to complete, be cost prohibitive, and its noise would disrupt aquatic life and birds throughout the cofferdam construction and demolition. An alternative option was implemented on a trial basis to conduct a mechanical demolition of the caisson above waterline along with an implosion of the remaining caisson down to mudline. This had the clear advantage as a cofferdam was not needed, and the demolition project duration would be approximately 6 months, instead of several years for the cofferdam option. The potential impact on aquatic life and birds from the implosion was a concern, as the location is environmentally sensitive; however, measures were implemented to minimize these impacts. As presented in this paper, this demolition option was implemented on a trial basis for Caisson E3. The technique succeeded and will now be used on the remaining caissons.BACKGROUND INFO ON CAISSON E3The reinforced concrete Caisson E3 is the largest caisson which supported the former East Span of the Bay Bridge. It was constructed in 1934, with the Bay Bridge opening in 1936. Figure 1 shows the project location. The caisson had a cell arrangement of 7 x 2 above the mudline. Below mudline, the caisson had a cell arrangement of 9 x 4. A structural transition was made between the 7 x 2 and 9 x 4 cell arrangements with buttress walls. All cells were flooded, as underwater openings were included in the original caisson walls to equalize the hydrostatic pressure. Figure 2 shows the caisson layout with limits for mechanical demolition and for the implosion."
Citation

APA: Michael Gebman Jack Gerwick  (2016)  Removal of the Former San Francisco-Oakland Bay Bridge Foundation Caisson E3 by Mechanical Means and Explosives

MLA: Michael Gebman Jack Gerwick Removal of the Former San Francisco-Oakland Bay Bridge Foundation Caisson E3 by Mechanical Means and Explosives. Deep Foundations Institute, 2016.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account