Secant Pile Barrier Wall Overlap, Thickness, and Position at the U.S. Army Corps of Engineers Wolf Creek Dam, Jamestown, KY

- Organization:
- Deep Foundations Institute
- Pages:
- 9
- File Size:
- 3481 KB
- Publication Date:
- Jan 1, 2015
Abstract
"Treviicos-Soletanche Joint Venture (JV) and the US Army Corps of Engineers (USACE) have installed a 3800-foot long, 275-foot deep and minimum 2-foot wide secant pile barrier wall at Wolf Creek Dam in Jamestown, KY. This paper describes the methodology employed by the JV and USACE to evaluate the overlap, thickness, and position of the barrier wall. It addresses the contractual requirements, positional uncertainty, and evaluation procedures.These procedures evolved over the course of the project as various issues were identified and procedures developed to evaluate these issues. During the project, it became clear that the JV and USACE could ascertain that the wall thickness and overlap requirements could be met if the overlap based upon Koden data was at least 0.7’ in the left-right direction. For a small number of piles with overlaps between 0.5’ and 0.7’, the piles are contractually compliant yet contain a minor degree of uncertainty in the overlap. Initially, the USACE assumption was that the amount of uncertainty of verticality measurements would require more than a 1-foot measured overlap in the left-right direction to confirm an actual, contractual 6-inch overlap. With time and experience, the limit of measured overlap was reduced in accordance with greater understanding of the equipment capabilities and tolerances. Other lessons learned include the need for Quality Control/Assurance personnel to collect data at the same starting point for every pile.For every pile the JV and USACE compared analog and digital data to provide confidence that the correct digital data was used for overlap calculations. Perhaps the most important lesson learned was the importance of the JV and USACE working together and sharing all data. Overlap analysis was performed by the JV’s Barrier Wall Specialist and a small number of USACE personnel. This resulted in a high level of experience and expertise within a small group.IntroductionThe Treviicos-Soletanche Joint Venture (JV) and the US Army Corps of Engineers (USACE) have installed a 3800-foot long, 275-foot deep, and minimum 2-foot wide secant pile barrier wall at Wolf Creek Dam in Jamestown, KY. The wall was installed through a 6-foot wide Protective Concrete Embankment Wall (PCEW) which was installed two feet into rock. The PCEW protects the embankment from erosion of drilling fluids during subsequent operations. Below the PCEW the piles were installed to a specified elevation (staggered at 475’ and 473’ below the 748.2’ work platform). The Ordovician limestone and shale bedrock is flat lying with few vertical fractures. These conditions facilitate the advancement of pilot holes with very low deviations (with considerable credit to the JV’s drillers and steering engineers). The pilot holes were spaced on 31.5-inch and 35-inch spacing. Subsequent enlargement of the pilot holes to 50’ resulted in a continuous wall. This paper addresses the requirements and procedures to assure that the wall was as wide, deep and continuous as specified."
Citation
APA:
(2015) Secant Pile Barrier Wall Overlap, Thickness, and Position at the U.S. Army Corps of Engineers Wolf Creek Dam, Jamestown, KYMLA: Secant Pile Barrier Wall Overlap, Thickness, and Position at the U.S. Army Corps of Engineers Wolf Creek Dam, Jamestown, KY. Deep Foundations Institute, 2015.