Sensitivity Analysis For Mining Projects

The American Institute of Mining, Metallurgical, and Petroleum Engineers
John C. Robison
Organization:
The American Institute of Mining, Metallurgical, and Petroleum Engineers
Pages:
3
File Size:
142 KB
Publication Date:
Jan 1, 1985

Abstract

INTRODUCTION Sensitivity analysis is a means of gauging the impact of individual risks on a financing. Key risks can occur in three time periods: - Feasibility, engineering and construction phase; - Start up phase (usually through completion); - Operating phase (post completion). If a company has agreed to cover these risks prior to completion, then less attention will be paid to the sensitivity of the project in the first two time periods. Since the operating phase of the project generates cash for both operations and debt service and generally does not begin until two to six years after the loan is signed, it is wise to look at scenarios other than the projected "base-case" scenario in order to determine the project's capability to operate successfully under a broad range of probable future events. Lenders are compensated at a fixed spread over their borrowing base and generally are not compensated if the project is successful beyond expectation. They are also subject to the loss of principal plus funding costs if the project performs below expectation. Because of this, lenders establish sensitivities around the parameters of conservative projections developed in the project feasibility studies and the cash flows resulting from these projections. The initial cash flow projections should demonstrate the project's ability to meet cash costs, debt service requirements (principal and interest), and still have sufficient cushion to cover contingencies such as strikes, price fluctuations, force majeur situations, etc. (See Schreiber, Chapter 10). The selection of the level of sensitivity analysis to be performed is the result of both objective criteria, including probabilistic analysis applied to the technical parameters, and, of equal importance, subjective criteria applied by the analysts, especially with regard to the economic and financial parameters impacting the project cash flows. RISK SENSITIVITY Assumptions used in the cash flow projections should be realistic. Risks identified by the lenders should be identified and cash flows prepared to assess whether these project risks are acceptable. Typical project risks include the following (see also Chapter 9): - Sufficient reserves - quantity and quality - Product price - Production level - Operating costs - Availability of energy and supplies - Transportation and infrastructure requirements and costs - Interest rate - Completion risks - Tax level - Political risks - Cost over-run risks - Operator experience - Management - Technological risks - Environmental permits and risks - Foreign exchange risks - Insurance coverage - Equity of sponsors - Inflation rate - Capital expenditure during project life In order to see the effect on the cash flow projections, each risk should be analyzed for its impact on the cash flow generating capacity of the project. Sensitivities can be examined to see if the resultant cash flow projection will meet the lenders minimum credit standards. 1.Reserve Sensitivity In general, lenders will not assume the reserve risk. However, it should also be noted that lenders receive loan proposals in which reserves range anywhere from proven to possible. Sensitivities are not generally run for various reserve levels and reserve estimates are either considered acceptable or not acceptable by the lenders.
Citation

APA: John C. Robison  (1985)  Sensitivity Analysis For Mining Projects

MLA: John C. Robison Sensitivity Analysis For Mining Projects. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1985.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account