Stripping of the Southern Exhaust Airway at Mount Lyell

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 2
- File Size:
- 233 KB
- Publication Date:
- Jan 1, 1974
Abstract
In the latter half of 1973 a contract was given to Roberts-Holland Joint Venture for the stripping of the southern exhaust airway.The contract was carried out efficiently and relatively cheaply. It was completed 2 months ahead of schedule.The sinking stage and in particular the drilling jumbo proved to be a success and helped produce an above schedule stripping rate.No major problems were encountered with ground conditions or ventilation. A survey of the shaft showed the diameter to be within the set limits of 5·49 m ± 0·15 m.