Stub Pier Stabilization Performance

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 560 KB
- Publication Date:
- Jan 1, 2017
Abstract
"Landslide activity along U.S. 50 in Cincinnati, Ohio (USA) has caused roadway damage for decades. After a necessary closure of three lanes due to slope movements, emergency stabilization measures were undertaken to protect the roadway by providing a short-term solution necessitated by The Ohio Department of Transportation budget constraints. The landslide shear plane occurred on a sloping bedrock surface as much as 50 feet below grade. Drilled shafts were installed 40 feet downslope of the roadway shoulder and were heavily reinforced across the shear plane but steel reinforcing did not extend the full length of the shafts and was stopped well short of the ground surface. Instrumentation data has been collected for 11 years after construction has shown these “Stub Piers” have provided much more than a short-term solution and have provided an attractive alternate to conventional deep shafts or tieback drilled shaft options.INTRODUCTIONLandslide activity has occurred along U.S. Route 50 in western Cincinnati, Ohio for many decades. The site is located between North Bend and Addyston, Ohio on the right descending (cutting) bank of the Ohio River. Road distress caused by slope movements required periodic repairs over recent decades. Railroad tracks downslope of the roadway also showed signs of horizontal displacement and periodic repair. Visual evidence in 2005 suggested the shear plane extended below the US 50 roadway and extended out into the Ohio River.A weed and brush-covered slope extended down slope from the roadway at about 3H:1V for a vertical distance of about 20 feet. Above US 50, the hillside continued to rise more than 100 feet. There is a railroad right-of-way at the toe of the slope with the Ohio River bank just downslope of the railroad.In 2005, Terracon Consultants was retained by the Ohio Department of Transportation (ODOT) to perform a geotechnical study that included 17 test borings and inclinometer monitoring at 4 locations. Roadway damage was occurring (see Figure 1). After only a few weeks of monitoring, the inclinometer casings sheared off about 50 feet below grade, near the soil / bedrock interface (see Figure 2). Soon after, the roadway distress worsened, causing ODOT to close 3 of the 4 lanes to traffic and reroute traffic onto the remaining single lane and shoulder. Terracon was asked to develop a stabilization design under emergency repair conditions. However, both limited budget and time-related constraints necessitated a direction by ODOT that the solution be at least “pseudo” short-term (3 to 5 years)."
Citation
APA:
(2017) Stub Pier Stabilization PerformanceMLA: Stub Pier Stabilization Performance. Deep Foundations Institute, 2017.