Supported Excavation Movement Causing Lateral Displacement and Cracks in Drilled Shafts - Lessons Learned from a Case Study in Chicago

Deep Foundations Institute
Amaneh E. Kenarsari Eric R. Borys Brett Gitskin
Organization:
Deep Foundations Institute
Pages:
10
File Size:
1583 KB
Publication Date:
Jan 1, 2018

Abstract

This case study discusses impacts of excessive Earth Retention System (ERS) lateral movement at a project in city of Chicago. The ERS (cantilevered sheeting) moved inward towards the excavation and caused lateral displacement and cracks in six drilled shafts located about 1 to 2 lateral feet (0.3 to 0.6 m) from the face of the sheet pile wall. Up to 9 inches (23 cm) of horizontal movement was observed on top of the supporting sheet-pile. Similarly, survey measurements showed the top of the drilled shafts moved laterally up to 8 inches (20.3 cm). To evaluate the cause of failure and determine a remediation solution, the soil, shaft and site conditions were investigated. Pile Integrity Tests (PIT) were conducted at the affected drilled shafts. The shafts with identified anomalies were cored and video-recorded. The cause of the failure was determined to be related to variable soil conditions across the site, deeper excavation (i.e., increased effective ERS wall height), and other differences between design and as-built conditions. Internal bracing, in the form of walers and rakers, was installed to limit further movement of the sheet pile as a short-term solution, with additional grade beams framed into the basement slab-on-grade as a long- term solution. Five of the six cracked shafts were spliced with reinforcing bars and high strength grout and one shaft was replaced. INTRODUCTION The subsoil in the Chicago Area mostly consists of glacial till clays underlain by water-bearing granular soil over bedrock. The glacial clays have very soft to medium consistencies for a typical thickness of 30 to 50 feet (9.1 to 15.2 m) below which hard clays (Hardpan, i.e., heavily over-consolidated clay soils) are encountered. The soft clays are often referred to as the “Chicago Blue Clay”. Beach Sands are also found above upper soft clays in several areas, especially within a three-mile strip near Lake Michigan (Peck and Reed 1954). Due to the existence of soft clay in Chicago area, supporting the mid to high rise buildings on drilled shafts extended to Hardpan is a common practice in modern building design. In the early 19th century it used to take about 3 weeks to excavate 1 shaft hole and about 1½ days to fill the shaft with concrete in Chicago (Manierre 1916). The early 19th century methodology of excavating a shaft consisted of hand digging the shaft, installing wood lagging as temporary shoring with spoils removed with a rope and pulley system from the surface. Today, the excavation of a typical drilled shaft in Chicago uses heavy drilling equipment and requires much less time for excavation and concrete placement. It is not uncommon for contractors to excavate shafts and place concrete at a rate of about 2 to 5 drilled shafts per day (with one drill rig).
Citation

APA: Amaneh E. Kenarsari Eric R. Borys Brett Gitskin  (2018)  Supported Excavation Movement Causing Lateral Displacement and Cracks in Drilled Shafts - Lessons Learned from a Case Study in Chicago

MLA: Amaneh E. Kenarsari Eric R. Borys Brett Gitskin Supported Excavation Movement Causing Lateral Displacement and Cracks in Drilled Shafts - Lessons Learned from a Case Study in Chicago. Deep Foundations Institute, 2018.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account