TBM Recovery Shaft Construction - SR-99 Tunnel

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 2164 KB
- Publication Date:
- Jan 1, 2016
Abstract
"The 17.4 meter (57 ft) diameter tunnel boring machine (TBM), the world’s largest at the time of her launch in 2012, locally referred to as “Bertha,” is stuck. Incapacitated due to mechanical failure approximately 36 meters (120 ft) beneath downtown Seattle, situated precariously between the deteriorating Alaskan Way Viaduct and the failing Seattle Seawall. Accessing Bertha with a vertical shaft provides the best approach to address all facets needed for repairs and will allow the full removal of Bertha’s cutter head and related inner workings. Limited area above the tunnel alignment and the physical restrictions of existing infrastructure, create significant challenges for the design of an otherwise symmetrical shaft, requiring special attention to design and layout. Consequently, the access/recovery shaft design required a combination of 3m, 2.5m, 2.2m, 1.5m and 1m diameter unreinforced drilled secant piles coupled with various ground improvement techniques and dewatering, to fully satisfy the shoring design requirements. This paper will describe the shaft installation procedures, equipment used and pitfalls encountered while undertaking access shaft construction of this magnitude.INTRODUCTIONTunneling on Seattle’s SR99 tunnel project began in July of 2013. After slowly mining through a 4.5 m (14.76 ft) thick fiber-reinforced concrete headwall and the first of three stabilized “safe havens,” Bertha would proceed along the proposed alignment through 122 meters (400 ft) of jet grout improved soil at a rate of slightly over 1.6 m (5.25 ft) per day. Once past the improved area, it was planned that “Bertha” – would be moving at a rate of about 11 m (36 ft) per day. By the end of October 2013, Bertha had mined roughly 131 m, (430 ft) averaging 1.4 m (4.6 ft) per day and had begun mining within native soils. By December 2013, tunneling had reached the 244 m mark and Bertha was averaging 3.6 m (11.8 ft) per day, achieving as much as 12.8 m (42 ft) of progress on given days. Unfortunately, on December 6th, 2013, Bertha began to stumble and all progress quickly came to a halt.It was initially reported that an obstruction had stopped Bertha in her tracks. The preliminary investigation involved installation of 10 deep dewatering wells to reduce the hydrostatic pressure around the TBM, and allow visual inspection of the cutter head from within the TBM, and also to investigate for the presence of obstructions at the face of the cutter head. During this inspection, fragments of steel pipe were discovered entangled in the cutter head. The fragments were apparently from an abandoned 254 mm (10 in.) diameter monitoring well casing, previously installed by WSDOT to monitor ground water conditions for the design and planning of this tunnel project. After the steel was removed from the cutter head and cleared from Bertha’s path, tunneling resumed. It was then discovered that Bertha was only able to generate a slow crawl."
Citation
APA:
(2016) TBM Recovery Shaft Construction - SR-99 TunnelMLA: TBM Recovery Shaft Construction - SR-99 Tunnel. Deep Foundations Institute, 2016.