The Final Piece of the Puzzle: Re-Design Of Grouted Closures for a Dam Cutoff Wall

- Organization:
- Deep Foundations Institute
- Pages:
- 12
- File Size:
- 1118 KB
- Publication Date:
- Jan 1, 2019
Abstract
Buckeye Lake Dam was substantially remediated between 2015 and 2018 as a result of unacceptable dam safety performance. A permanent seepage cutoff, consisting primarily of a soil mixed cutoff wall (SMCW) with occasional sections of steel sheet piling, was constructed along the dam alignment. Closures were required at the terminus of the soil mix elements with existing structures or coffer cells, and at locations where new sheet piling was constructed parallel to the new soil mixed cutoff wall, creating a short circuit seepage path. The original proposed design to construct these closures included permeation grouting methods with chemical grouts. However, a combination of multiple chemical grout types, multiple grout pipes, and an extensive post-grouting verification program was required to ensure the design intent was achieved. After award of the project, the specialty grouting contractor elected to evaluate jet grouting as an alternative closure construction method. The advantages of the jet grouting option offered potential schedule and cost savings to the project as well as a superior product for seepage reduction, given the mixed soil conditions at the site. This paper presents an examination of the site conditions and project goals for the construction of the proposed closure elements for the rehabilitation of Buckeye Lake Dam. Descriptions of the original and alternative treatment methods are provided, with expected performance results. A description of the relative strengths and deficiencies of each method, as well as the feasibility and constructability of each method is provided. The implementation of the jet grouting program is presented, including a discussion of the design elements, quality control test methods, movement monitoring, and verification test methods. This paper also examines the risks associated with jet grouting and how those risks were mitigated during the grouting operations.
HISTORY
Buckeye Lake is situated approximately 28 miles east of Columbus, Ohio and is managed and operated by the Ohio Department of Natural Resources (ODNR) as part of the Ohio State Parks system. The lake is impounded by natural features that exist along the south and east banks of the reservoir, and by the embankment structure constructed along the north and west banks of the reservoir (see Fig. 1). The reservoir site was originally a natural swamp and the original purpose of the constructed dam and reservoir was to provide water to the Ohio and Erie Canal System. Several dam alignments and configurations were constructed during its early history; however, the original embankment is comprised of homogeneous earthen fill. The embankment is 15 ft (4.6 m) high and extends 4.1 miles (6.6 km) from the North Shore abutment along the east, continuing to the abutment at Lieb’s Island to the West. Several spillway and outlet structures exist along the embankment alignment. Most noteworthy are Seller’s Spillway and Amil Spillway. Fig. 2 is a Plan View of the embankment alignment and appurtenant structures at Buckeye Lake.
Citation
APA:
(2019) The Final Piece of the Puzzle: Re-Design Of Grouted Closures for a Dam Cutoff WallMLA: The Final Piece of the Puzzle: Re-Design Of Grouted Closures for a Dam Cutoff Wall. Deep Foundations Institute, 2019.