Tunneling Under Highway 401: Construction of Large Diameter Pre-Support Pipe Canopy - RETC2021

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 13
- File Size:
- 4289 KB
- Publication Date:
- Jun 13, 2021
Abstract
Toronto Tunnel Partners (TTP), under contract to Metrolinx/IO, is constructing new twin rail tunnels under the Highway 401 & 409 interchange to accommodate additional tracks to support the GO Expansion program for future two-way, all-day service. The new tunnels are being constructed using the Sequential Excavation Method (SEM) and utilize a tunnel pre-support system consisting of a series of 800 mm diameter steel pipes to form a pipe canopy. The pre-support pipes were installed with an Auger Boring Machine (ABM) in four separate headings; one heading from each of the tunnel end portals, and two from a shaft in the middle of the highway. To facilitate the auger boring operation, a custom steel reaction frame was required to counteract the thrust from the ABM at the portals, and a temporary shaft structure was installed in a narrow median space of the highway. The installation of the pipe canopy had to overcome challenges including removal of obstructions, alignment issues, and controlling settlements to the highway surface. This paper discusses the purpose of the pipe canopy, design and installation of the temporary shaft and structures to support the auger boring operation, the experience of the contractor during the installation of the pipes, and brief overview of the experience tunneling below the pipes.
Citation
APA:
(2021) Tunneling Under Highway 401: Construction of Large Diameter Pre-Support Pipe Canopy - RETC2021MLA: Tunneling Under Highway 401: Construction of Large Diameter Pre-Support Pipe Canopy - RETC2021. Society for Mining, Metallurgy & Exploration, 2021.