    Approximating diamond drill rod wear

    By R. Laplante, P. Radziszewski, P. De Ciccio

    "Predicting the effect of wear can lead to improved control strategies that can possibly minimize the risk of catastrophic failure due to wear while maximizing useable life. In the field of geological

    Jan 1, 2002

  • CIM
    Factors Affecting the Dissolution of Gold from Refractory Flotation Tailings

    By H. U. Ross

    "INTRODUCTION Extensive studies have been carried on pure gold to determine the various factors that affect its dissolution in alkaline cyanide solutions. With the extension of milling to refractory o

    Jan 1, 1973

  • CIM
    Dynamic Testing of Friction Rock Stabilisers

    A rough simulated borehole has been developed for the installation and dynamic testing of rock bolts a the WASM Dynamic Test Facility. The rough simulated borehole is used for rock bolts that are sens

    May 1, 2009

  • CIM
    Acid mine water treatment at Les Mines Gallen, Noranda Mines Limited

    By N. Lecuyer

    "During early 1980, pre-production work commenced at the ""Les Mines Gallen"" project, north of Noranda, Quebec. As a result of the acid mine water associated with this property, a major pre-productio

    Jan 1, 1983

  • CIM
    An Economical Vertical Transport System to Hoist 3 Mt of Ore per Annum from 1640 m

    By Wendy L. Naysmith

    This paper deals with the various options considered and factors that influenced the final selection of the headframe, shaft layout and hoisting systems required at the Impala No 16 Shaft in order to

    Oct 1, 2010

  • CIM
    Fire protection for mine surface coal handling systems

    By T. G. Carter

    "During the early part of the 1980s, four new surface coal mines commenced operation in the Province of British Columbia. Each represented a major investment in both persons and materials in order to

    Jan 1, 1988

  • CIM
    Costello Mine

    By Perry L. Christian

    "Mana/ta Coal Ltd. 's Costello Mine, located seven kilometres east of Estevan, Saskatchewan, has been operating at the present location since 1960. During the past twenty-three years, annual productio

    Jan 1, 1985

  • CIM
    Particle Bee Algorithm for Tower Cranes Layout With Materials Quantity Supply and Demand Optimization

    By L. C. Lien

    Tower crane layout (TCL) is a typical construction site layout (CSL) problem, which is suitable for a wide range of work assignments and site conditions. Tower crane is one of the key facilities for v

    Aug 1, 2013

  • CIM
    An Innovative Process for the Separation of Iron in Mixed-Chloride Medium: A Case Study for Lateritic Ore

    By M. A. Halim, V. I. Lakshmanan, Z. Jankovic

    An innovative mixed-chloride process for the separation of iron from lateritic ore is described. The separation of Fe(III) from leach liquor is an important process step for the recovery of nickel and

    Jan 1, 2015

  • CIM
    Decommissioning Pits with Ecological Engineering

    By M. Kalin

    "Ecological Engineering, a biotechnological approach to the decommissioning of base metal mining wastes, is being tested on two pits (Gloryholes) in Newfoundland, Canada. Pit #2 has an average pH of 3

    Jan 1, 1992

  • CIM
    Rock Mass Classification for Pre-Excavation Support Planning and at-Face Excavation Performance Assessment

    The rock mass classification systems were developed for different functions, including support selection, excavation method selection and the determination of rock mass engineering properties for exca

    May 1, 2009

  • CIM
    Chapter 9. Royalty Agreements

    By Karl J. C. Harries

    "9.1. INTRODUCTIONIn Chapter 5 of Volume I royalties are dealt with and several topics would appear to be duplicated in this Volume. However, Volume I may be looked upon as a general guide, whereas th

    Jan 1, 2003

  • CIM
    Utilizing titanium to successfully handle chloride process environments

    By R. W. Schutz

    "Titanium possesses an exceptional and wide-range resistance to chlorides and their compounds when compared to most corrosion-resistant engineering alloys (CRAs) used in the chemical process industry.

    Jan 1, 2002

  • CIM
    Stamp-Milling and Amalgamation Practice at Goldenville, N.S. (fb013ab7-b931-4c07-a28c-bfdc18236a53)

    By E. H. Henderson

    MR. R. V. NEILY stated that he had at one time operated at Goldenville. The practice and results are much the same now as in the olden days. Inside plates were then found to be a source of trouble and

    Jan 1, 1935

  • CIM
    Application Practice of Bottom Blowing Continuous Converting to Replace Copper P-S Converter

    By Hongfei Li, JianLong Wang

    This paper introduces the technical characteristics, transformation scheme and production practice of the project in which Copper P-S Converter was replaced by Bottom Blowing Continuous converting for

    Jan 1, 2019

  • CIM
    Jolu Gold Mine Low Cost Gold Recovery Configuration

    By J. Kazakoff

    "The success of gold recovery at the Jolu gold mill depends on many variables. The most important ones are the people, the ore body, plant design parameters, equipment selection and cost control. This

    Jan 1, 1990

  • CIM
    Environmental and Reclamation Measures at Equity Silver Mines Ltd.

    By J. Patterson

    "Acid Mine Drainage (A.M.D.) formed from oxidation of disposed pyritic wastes presents a potential pollution hazard for Equity Silver Mines Limited and the mining industry in general. Failure to colle

    Jan 1, 1988

  • CIM
    Numerical Analysis of the Rock Cutting Process and the Loading of Cutting Tools

    By M. Gimpel, R. Galler, T. Antretter, H. Kargl, M. Mikl-Resch, R. Tichy, W. Ecker, G. Pittino

    "A computational method based on a continuum-mechanical approach to simulate rock cutting is developed and evaluated. The aim is to obtain the local loading acting at the cutting pick during operation

    Jan 1, 2015

  • CIM
    The Recovery of Rare Earths, Uranium and Pyrite from Pele Mountain’s Proposed Eco Ridge Mine Project

    By Roger Payne, John R. Goode, Feng Gao, James Brown

    The Eco Ridge deposit is located in the Elliot Lake mining camp in Northern Ontario, Canada. Between 1955 and 1996, the area produced more than 138,000 t (300 million pounds) of U3O8 and very signific

    Jan 1, 2014

  • CIM
    Géologie de la Mine Doyon, Cadillac, Québec

    By Pierre Sauvé, Guy Perrault, Armand Savoie, Pierre Trudel

    "La Mine Doyon est une entreprise détenue à parts égales par Cambior Inc. et par Minerais Lac Ltée qui en est l'opérateur. Les statistiques de production au 1"" janvier 1990 indiquent que, depuis le d

    Jan 1, 1990