Computerized maintenance: making it work for youBy Rae Simpson
"This paper provides insight into the elements of computerized maintenance systems and identifies some of the factors which influence their effectiveness. The paper describes what to expect in terms o
Jan 1, 1988
-
Conveyor systems design and application for surface miningBy M. Scobie, T. Atkinson
"This paper reviews the development of new designs in extensible and high angle conveyor systems. These aim to overcome the limitations of prior alternative concepts in design. The application of such
Jan 1, 1991
-
Advancing Sudbury Exploration with 3D ModellingBy D. Richardson
Presentation Objectives ?Demonstrate the utility of 3D modelling for visualizing exploration data ?Demonstrate the target generation ability of 3D model query methods Exploration Criteria -Example
May 1, 2006
-
Potash Processing - A ReviewBy A. F. Banks
"The last time I spoke to you the potash industry was at a low point. Markets were bad and the industry depressed. Many people had left and there was very little being done in terms of development. Th
Jan 1, 1982
-
Centrifuge model studies of fill pressures on temporary bulkheadsBy R. J. Mitchell
"The use of hydraulically delivered classified tailings sands to provide ground support in large mining operations is still widespread despite recent developments of alternate backfilling methods and
Jan 1, 1992
-
Erosion Control Hollinger Mine Tailing SiteBy I. M. Gordon
"INTRODUCTIONThe Hollinger tailing disposal plant is situated about 1 1/4 miles south of the mill. The area available for tailing covers 620 acres and is roughly 1 ¼ miles long by ¾ mile wide.Tailing
Jan 1, 1969
-
Whitewood MineBy Howard Keele
"The Whitewood Mine near Edmonton, Alberta, is owned by TransAlta Utilities Corporation and operated by Manalta Coal Ltd. Approximately 2 million tonnes of sub-bituminous coal is supplied annually to
Jan 1, 1985
-
Restauration Du Site Minier Poirier (Joutel) - Expériences Acquises Et Suivi Des TravauxBy Richard Maurice
RÉSUMÉ La restauration du site minier Poirier, à Joutel s?est déroulée entre 1998 et 2001. Le principal élément des travaux a été la restauration du parc à résidus et des zones d?épanchement qui tot
Nov 1, 2002
-
Comminution by Conventional and Autogenous GrindingBy J. A. R. Faucher
"Autogenous grinding may be an efficient and economical solution to your ore comminution problem.An important potential economic advantage of autogenous mills results from the availability of very lar
Jan 1, 1969
-
Numerical Studies on the Bearing Capacity of Two Interfering Strip Footings Based on HOEK–Brown MaterialsBy M. Imani, A. Fahimifar, A. H. Javid
"Current studies of bearing capacity for shallow foundations tend to rely on the hypothesis of an isolated footing. In practice a footing is never isolated; it is mostly in interaction with other foot
Jan 1, 2015
-
Corrosion in the mining industryBy V. S. Sastri, G. R. Doey, R. W. Revie
"Different forms of corrosion, the various corrosive environments encountered, the mining equipment subject to corrosion and the methods to control corrosion in the mining industry are briefly reviewe
Jan 1, 1994
-
Fine Grinding, a RefresherBy A. G. Doll
"Many power-based grinding models exist, and most operators are familiar with Fred Bond's ""third theory"". Bond's model is most commonly used to describe primary and secondary grinding to product siz
Jan 1, 2017
-
An Expert System Supervisor of a Flotation CircuitBy A. L. Mular, R. P. Edwards
"The operation of flotation circuits is often regarded as a combination of art and science. Expert systems offer a method by which the art may be captured and supervisory control of flotation circuits
Jan 1, 1991
-
Malartic Gold Fields MineBy R. A. Halet
"The Malartic Gold Fields mine is a good example of the association of ore deposits with a major fault zone. It also exemplifies the control exerted by the physical and chemical character of the host
Jan 1, 1954
-
General Discussion - Impurity Penalties in Smelter ContractsBy G. C. McKerrow
"Mr. G.C. McKerrow, Assistant Manager of Noranda Mines and formerly Smelter Superintendent attended the meeting to answer questions as to why smelters imposed penalties for too much zinc in a copper c
Jan 1, 1971
-
Economic Analysis of Crushing System in Metallurgical Slag Recycle SystemBy X. J. Luo, F. Zhang
"Metallurgical slag (MS) such as steel slag, copper slag is a renewable resource and its compressive strength exceeds 200MPa in general. Because pure metal slug can easily be mixed into MS, complex re
Jan 1, 2016
-
Process Development for the Recovery of Critical Materials from Electronic WasteBy P. Keller, T. E. Lister, G. G. Clark, L. A. Diaz
As electronic technology continues to evolve there is a growing need to develop processes which recover valuable material from antiquated technology. This need follows from the environmental challenge
Jan 1, 2016
-
Target vectoring using lithogeochemistry: Applications to the exploration for volcanichosted massive sulphide depositsBy Alan G. Galley
"Advances in our knowledge of the petrochemical attributes of deposit environments and of the character and extent of hydrothermal systems associated with certain deposit types has resulted in increas
Jan 1, 1995
-
Inflation in project evaluation (05075753-63cb-41a5-ba9e-814572deac03)By L. D. Smith
"Those who submit competing proposals for projects seek to present senior management with complete and fully supported material that will not fail under questioning. Hopefully, misleading notions and
Jan 1, 1990
-
Commissioning and Testing of Thickener Feed De-Aeration Cyclones at the Xstrata Nickel Raglan OperationBy Colin Hardie, Simon Pelletier, Rakan Rhabani, Guy Comeau
"In order to improve the nickel concentrate thickener operation at Raglan Mine, two pulp deaeration cyclones were installed. These units obtained from Outotec Pty Ltd, also called the FrothBuster®, ha
Jan 1, 2008