    Trench Cutter - The Multi Purpose Solution

    By Alexander Blatt, Franz-Werner Gerressen

    Power Point Presetation at DFI 2022

    Sep 1, 2022

  • DFI
    Construction of a Very Flexibility, Impermeable, Bituminous Membrane Seepage Barrier, to Connect an Existing Concrete Dam Structure to a Newly Constructed Abutment Cut-Off Wall

    By Brian Wilson, Megan Atkinson, Richard Diggle, Nathan Sweeney

    "Ruskin Dam, located near Mission, British Columbia, was constructed in 1929 and 1930 and comprises of a concrete gravity dam structure founded on bedrock. At the right abutment, which consists mostly

    Jan 1, 2017

  • DFI
    Case Study: Natomas Levee Improvement Program Cutoff Walls

    By Matthew D. Marks

    The Sacramento Area Flood Control Agency initiated the Natomas Levee Improvement Program in 2006 which would bring the entire 42 mile Natomas Basin perimeter levee system into compliance with applicab

  • DFI
    Case Study: Natomas Levee Improvement Program Cutoff Walls

    By Matthew D. Marks

    "The Sacramento Area Flood Control Agency initiated the Natomas Levee Improvement Program in 2006 which would bring the entire 42 mile Natomas Basin perimeter levee system into compliance with applica

    Jan 1, 2017

  • DFI
    Large Diameter Helical Piles for Refinery Expansion

    By Chris Normand, Paul Volpe, Eric Wey, Howard Perko, Burt Ogilvie, Patrick Murray

    "A refinery expansion project for Marathon Petroleum Company in Southern Louisiana required existing medium to large pipe racks to be expanded for additional capacity. Foundation modifications were ne

    Jan 1, 2017

  • DFI
    Doyle Drive – Extreme Pile Installation

    By Peter Faust

    "The south access road to San Francisco’s Golden Gate Bridge, known as Doyle Drive or Presidio Parkway, needs to be replaced. Built in 1936, it is the primary highway and transit linkage through San F

    Jan 1, 2012

  • DFI
    Design And Construction Of Shear Pins For Landslide Stabilization

    By Fei-chiu Huang

    A 17-acre landslide occurred in February 2001, on a slope below Via Bellota in the City of San Clemente, California. Three homes were destroyed and many others placed in jeopardy. The landslide, inv

    Jan 1, 2010

  • DFI
    Measurements of CDSM Strengths and Seepage Data Following Seismic Upgrades of San Pablo Dam

    By Atta B. Yiadom, A. David Miller, Robert C. Kirby, Sean M. Todaro

    "San Pablo Dam is a 170-foot (52-meter)-high earthfill embankment, located approximately 10 miles (16 kilometers) north of downtown Oakland, California, that impounds a 38,600 acre-feet (47.6 million

    Jan 1, 2015

  • DFI
    Seepage Barrier Mix Design Development, Installation, and Evaluation

    By George W. Little, John Councilman

    "The selection, evaluation, and modification of contractor mix designs for self-hardening seepage barriers, completed by the slurry trench excavation method, can be one of the most critical and challe

    Jan 1, 2016

  • DFI
    Data Drives Herbert Hoover Dike (Hhd) Rehabilitation Efforts

    By Michael Arnold, Jignyash Manyam, Yoav Rappaport

    The USACE required construction of over 13 miles of cutoff wall at an average depth of 65 feet for the Herbert Hoover Dike (HHD). To meet project requirements, to provide quality control and make soun

    Oct 1, 2022

  • DFI
    Jet Grouted Foundation for 57-Story Tower

    By Robert Alperstein, Nidal AbiSaab, Joe Pastore

    "This paper describes the design and construction aspects of the foundation support for a 57-story building currently under construction in lower Manhattan. The site is located near the East River wit

    Jan 1, 2016

  • DFI
    Case Study: Feather River West Levee Program Cutoff Walls

    By Kyle R. Lackner, Jared P. Williams

    "The Sutter Butte Flood Control Agency initiated the Feather River West Levee (FRWL) Program in 2010 to bring 35 miles of levee along the Feather River into compliance with applicable Federal and Stat

    Jan 1, 2016

  • DFI
    Construction of a Ground Improvement Scheme to Support Large Mechanically Stabilized (MSE) Earth Walls in Kitimat, BC – Using Cutter Soil Mixing

    By James Coull, Brian Wilson, David Siddle

    "In 2012, Golder Construction Inc. was awarded a Design-Build contract for the design and construction of an extensive, deep ground improvement scheme to support up to 20 metres (66 ft) high Mechanica

    Jan 1, 2017

  • DFI
  • DFI
    Vsm And Ofd® Technology: Mechanized Solutions For Deep On- And Offshore Foundations

    By Nils Schneider, Marc Peters, Stefan Frey, Andrea Fluck

    Due to the worldwide population growth, the development of sustainable infrastructure and the exploration of renewable energies plays a key role to handle the rising megacity trends and to limit carbo

    Nov 1, 2022

  • DFI
    Building Drilled Shafts to Bridge the Mississippi

    By Brian Koch

    Michels installed 242 drilled shafts to support the piers for a new basket-handle, true-arch twin bridge across the Mississippi River from Moline, IL to Bettendorf, IA. The installation of the drilled

    Jan 1, 2019

  • DFI
    Performance Based Excavation Support Design For Challenging Urban Site Geometry In Toronto, Canada

    By Shawna Munn, Carol Dounitch, Erika Acton

    The EQ Bank Tower, a 24-storey office tower with 4 levels of underground parking, is currently under construction at 25 Ontario Street in the downtown core of Toronto, Canada. The tower geometry requi

    Oct 1, 2022

  • DFI
    Applications of Diaphragm Wall Technology for Deep Foundations and Permanent Underground Structures for the Transbay Transit Center and the Transbay Developments

    By Mikael Calando, Thomas Joussellin

    "San Francisco's rapid growth has caused the city to plan for the Transbay Transit Center Project, a visionary transportation and housing project, that will transform downtown San Francisco and the Sa

    Jan 1, 2016

  • DFI
    Soil Cement Tensile Strength and Modulus as a Function of Unconfined Compressive Strength

    By Dominic Parmantier, Jason Page

    "In the past, the designers of DSM have analyzed various failure modes and then specified a minimum unconfined compressive strength (UCS) for the soil-cement. The specified minimum UCS reflected the c

    Jan 1, 2015

  • DFI
    Cut-Off-Wall Welzow in the Lausitz, Germany, a 400 Feet (120 M) Deep Hydraulic Barrier between an Existing Lake Region and an Open Pit Coal Mine

    By Stephan Fisch, Franz-Werner Gerressen

    "The use of cut-off-walls (COW) for the open pit coal mines has been used for decades. They have been used to reduce the negative hydraulic impact to the surrounding area caused by the open pit mining

    Jan 1, 2017