    Construction Methods and Quality Outcomes for Bored Cast-in-Situ Piles – A Review of Current Practice

    By Jim Slatter, Ben Collingwood

    "It is well known that the adoption of an appropriate construction methodology is critical to quality outcomes for bored piles (drilled shafts). Many case studies have been published documenting quali

    Jan 1, 1900

  • DFI
    The Geo-Impuls Programme: Towards Reducing Geotechnical Failure in the Netherlands

    By Paul M. C. B. M. Cools, Martin Th. van Staveren

    In 2010, the 5-years joint industry programme Geo-Impuls started in the Netherlands. The ambitious goal of this programme is to reduce geotechnical failures in our civil engineering projects by half i

    Jan 1, 2017

  • DFI
    Drilled Shaft Inspector's Manual - 1.0 General - 1.1 Scope And Limitations

    The intent of this manual is to provide guidelines for inspectors of drilled shaft construction otherwise referred to as drilled piers, caissons or bored piles. It should also be helpful to train begi

    Jan 1, 2004

  • DFI
    Ground-Supported Working Platforms For Tracked Plants And Mobile Cranes – Investigations Of Intercaction Effects

    By Moritz Schleeh, Christian Moormann

    Temporary working platforms are generally required in order to ensure that heavy construction machinery such as drilling and trench wall units, pile drivers, vehicle and crawler cranes can be set up s

    May 1, 2022

  • DFI
    Hybrid Energy System Installed on Deep Mixing Barge

    By Kento Miyamoto, Kazuki Imamura, Takayuki Tanaka

    "Global economic development has drastically increased energy consumption in various fields, and CO2 emissions, which are a prime cause of global warming, have continued to increase. Therefore, measur

    Jan 1, 2015

  • DFI
    Controlling Thermal Stresses in Barrier Walls

    By Karsten Beckhaus

    Barrier walls in levees and dams are designed and constructed for new structures and for rehabilitation or upgrade of existing structures to control seepage. Construction methods applied are often dee

    Sep 8, 2021

  • DFI
    Engineering Foundation Support For Las Vegas Strip's Tallest Hotel Casino

    By Nicholas P. Gura

    This paper presents the analysis, design, and load test program results for drilled shafts to support a 70-story hotel tower and associated 10 story podium structures located in Las Vegas, Nevada. A

    Jan 1, 2007

  • DFI
    CFA Pile Design Parameters in Sand

    By Stuart Coutts

    "This paper presents an overview of the author’s experience related to the assessment of the base capacity of straight shafted and enlarged-base bored piles in sand. A design approach based on CPT qc

    Jan 1, 1900

  • DFI
    Professional Responsibilities In Sub-Surface Investigations For Foundations. - Introduction

    By D. J. Ketkar

    It is a frequent experience to find that the Sub-surface Investigation (S.I.) data is either inadequate or misleading. However, such cases are rarely reported. Nonetheless, the projects suffer on-acco

    Jan 1, 1996

  • DFI
    The Importance Of Tension Softening (Of Concrete) In Modelling Of Tension Piles

    By Qingwei Joshua Ong

    Tension piles, also known as uplift or anchor piles, are necessary to resist uplift forces that might cause structural distress. In excavation projects, most uplift forces are developed because of hyd

    Nov 1, 2022

  • DFI
    Data Drives Herbert Hoover Dike (Hhd) Rehabilitation Efforts

    By Michael Arnold, Jignyash Manyam, Yoav Rappaport

    The USACE required construction of over 13 miles of cutoff wall at an average depth of 65 feet for the Herbert Hoover Dike (HHD). To meet project requirements, to provide quality control and make soun

    Oct 1, 2022

  • DFI
    Prediction of Axial Geotechnical Resistance of Base Grouted Drilled Shafts

    By Emad Farouz, Ehab S. Shatnawi

    "The increasing demand for small deformations and high-capacity drilled shafts without enlarging drilledshaft diameters has motivated the development and increasing use of a base grouting (BG) techniq

    Jan 1, 2016

  • DFI
    You Can't Drive Piles Because Of The Vibration

    By Jerry A. Steding

    How many times have you heard "You can't drive piles because of the vibration."? You hear these words come out of the mouths of owners, engineers, and contractors. When a piling contractor he

    Jan 1, 1988

  • DFI
    Army Corps Mega Projects Benefits From Innovative Foundations

    By Dale Berner, Michael O’Sullivan

    "This paper focuses on lessons learned from the innovative designs, in-the-wet construction methodology and modified foundation conditions, for two United States Army Corps of Engineers, USACE, Megapr

    Jan 1, 2017

  • DFI
    Settlement Reducing Auger Cast-In-Place Piles below a Mat Foundation of a 41-Story Structure

    By Swaminathan Srinivasan, Aaron J. Muck

    "When an opportunity arises to combine state-of-the-art concepts with advanced modeling tools, engineers need to take what they know and apply forward thinking to geotechnical solutions to promote the

    Jan 1, 2015

  • DFI
    Case Study of Deep Mix Pile Supported Diaphragm Wall for a Stilling Basin Structure in Malaysia

    By Chandrasegaran, Tamilmani

    "This paper describes a case study of a retaining wall structure using a diaphragm wall to construct a stilling basin at Tanjung Bin T4 power plant in Johor Bahru, Malaysia. The stilling basin is part

    Jan 1, 2015

  • DFI
    Deep Foundation Support for the Iconic New York Wheel

    By Satyajit Vaidya, Rudolph Frizzi, Quadri Owokoniran

    "This paper presents a case history in the design and construction of high-capacity drilled shafts for the iconic New York Wheel presently being constructed along the St. George area waterfront in nor

    Jan 1, 2016

  • DFI
    As-Built Analysis - An Integral Part Of Pile Foundation Design

    By Dan Yang

    Pile foundation designs are performed routinely based on geotechnical information available at the time of design, often with due consideration of large uncertainties inherent to soils and site condit

    Jan 1, 2010

  • DFI
    Deep Soil Mixing Ground Improvement for the U.S. Federal Courthouse in Downtown Los Angeles, California

    By Roberto A. Lopez, Eric Lindquist, Jon Bussiere, Dean Iwasa

    "The new 11-story U.S. Federal Courthouse building in downtown Los Angeles demanded a cost effective foundation system capable of attaining a strict total settlement criterion of 0.5 inches (12 mm) un

    Jan 1, 2015

  • DFI
    Soil Fatigue Analysis for Pile Driving Simulations Using an Impact Hammer

    By Peter Middendorp, David J. Tara, Gerald E. Verbeek, Jan Fischer

    "For pile driving simulation the model used must be accurate for the entire process, i.e. from the start of pile driving until the pile has reached its target depth. Of the various model components (h

    Jan 1, 2017