Design-Build of Watertight Underground Structures for Tunneling in Miami, Florida - The Norris Cut Utility Relocation ProjectBy Eugene Mirsky, Eloy Ramos, May ElKhattab, John Wise, Terrence Carroll, Jose Torres
In 2017, Nicholson Construction Company completed a $72.1 million design-build contract for Miami Dade Water and Sewer Department to replace an existing 54-inch diameter pre-stressed concrete force ma
Jan 1, 2018
-
Jardim de Alah Station — Built in Olympic TimeBy Dario Libano, Luis Carlos Tenuta, Juliano Penteado
"Subway Line Number 4 is one of the newest additions to the Rio de Janeiro subway network. Built for the 2016 Olympic Games, the 16 km (10 mi) subway line connects the south of the city, with the famo
Jan 1, 2016
-
Construction, Inspection And Lessons Learned For 3.81-M Diameter CIDH Piles ? Richmond-San Rafael Bridge Seismic RetrofitBy A. R. Dover
The Richmond-San Rafael Bridge is a 6.92 kilometer (4.3 mile) long major toll bridge span that crosses the northern San Francisco Bay in a highly seismically active region. Tutor-Saliba / Koch / Tidew
Jan 1, 2008
-
Experiences With Heavy Drop Hammer Testing Of Rock-Socketed ShaftsBy Frank Rausche
Since the early 1980s, when the Road Construction Authority of Victoria authorized the dynamic proof testing of roughly 100 drilled shafts of 1.5 m diameter and typically 60 m length in Melbourne Aust
Jan 1, 2006
-
Stone Column Treatment and Elaborate Load Tests Verification for Improving Subsoil Conditions on a Large-Scale Residential Development ProjectBy Vijaya Bhushan Rao, Jason Redgers
A substantial lifestyle destination in the United Arab Emirates, in the Emirate of Abu Dhabi comprising of 1315 villas, town houses and non-residential leisure facilities is built over an area of 280
Sep 8, 2021
-
Jet Grouting for Groundwater Cutoff at Tie-in between Existing Tunnel and New ConstructionBy Aaron Evans, Chu E. Ho, Tom Richards
"This paper describes an innovative case history of using jet grouting to form a groundwater cutoff wall at the interface of a cut-and-cover construction and an existing tunnel. The design of the jet
Jan 1, 2016
-
Construction of Deep Shafts in Soft Ground for the West Side CSO Tunnel Project, Portland, ORBy Vince Luongo
"INTRODUCTIONThe West Side Combined Sewer Overflow (CSO) Tunnel Project is located in Portland, Oregon and is part of the Willamette River CSO Control Project. The purpose of the West Side CSO Project
Jan 1, 2006
-
Determination of Coefficient of Modulus of Sub-Grade Reaction for Free Head Short PileBy Sumit Kumar Biswas, Moyukh De, Sibapriya Mukherjee
"The piles often are also subjected to lateral (horizontal) forces and moments. In fact, there are some structures where the primary function of piles is to transfer lateral loads to the ground. Prope
Jan 1, 2015
-
High Strain Testing Of Augered Cast Piles At Miami Fort Power StationBy C. Michael Morgano
Static tests are costly and time consuming, so they are not always the best answer [ ]
Jan 1, 2005
-
High Capacity Drilled Cast-In-Place Piles, House Of Representatives Building, Lansing, Michigan - SummaryBy Robert C. Rabeler
Soil and Materials Engineers, Inc. (SME) has utilized drilled cast-in-place (D-CIP) piles on a number of projects in the midwest. These foundation systems have typically consisted of drilling an 8 to
Jan 1, 1999
-
Eglinton Crosstown, a New Step in Toronto’s Subway SystemBy Lars Richter, Franz-Werner Gerressen
"The Eglinton Crosstown Line was conceived as the Eglinton Crosstown LRT, a partially underground light rail line, announced in 2007 as part of the Transit City plan, which included the implementation
Jan 1, 2017
-
Session IV - Notable International Projects - Special Foundation Technique For The Intersection Of Two Canals Near Magdeburg, Germany - Summary:By Wolfgang G. Brunner
The closing of the gap in the European waterway- net is one of the big and challenging traffic projects following the German reunification. The water canals in the North German plain connect the Rhine
Jan 1, 2000
-
Design And Construction Considerations For The Use Of Slurry Walls To Construct Water Reservoirs In The Denver FormationBy Ken Andromalos
Continued population growth combined with limited water resources in the Denver area has resulted in the conversion of a number of mined out gravel pits in the area into municipal water storage facili
Jan 1, 2007
-
Automation Of Pile Foundation Design Post-Processing To Produce Pile PlansBy Rajasekar Subbian, Jessica Oudhof
In the Netherlands pile foundation design is done using CPTs in accordance with EC7 national annexure. The capacity per tip level is calculated for every CPT followed by zonation to find the tip level
May 1, 2022
-
Effects Of Mineral And Polymer Slurries On Drilled Shafts - 1. Introduction - 1.1 History Of And Principles Of Mineral Slurries In Drilled Shaft ConstructionBy Michael W. Neill, O&apos
Drilling slurry has become an effective aid to the construction of drilled shafts in caving and/or waterbearing soils. Historically, drilling slurry made of bentonitic clay and water was first used in
Jan 1, 1991
-
Foundation in Simsima Lime Stone for an Underground ReservoirBy Chandramohan P. V., Ravi Kishore
"An underground reservoir was to be constructed at Doha in Qatar. Simsima lime stone is present at the bottom. When the reservoir is empty, there will be uplift at the bottom but this will change to d
Jan 1, 2017
-
DFI 2008 Outstanding Project Award Winner Intricate Excavation for the New South Ferry Subway StationBy Alice Arana, David M. Cacoilo, Joel L. Volterra
"To make space for the new South Ferry Station in lower Manhattan, engineers and contractors carved out a new tunnel beneath three operating subway tunnels and tangentially to yet another tunnel. Crea
Jan 1, 2008
-
St Clair River Rail Tunnel, Sarnia Evolution Of The Design And Construction Methods For The TBM Cutterhead RetrievalBy Peter McDonald
In 1994 the world's largest underwater tunnel was constructed to link Canada and the U.S.A. This new tunnel was large enough to accommodate double-decker railway cars. The construction of an unpl
Jan 1, 1997
-
Foundations For The Sohio Corporate Headquarters - A Presentation At The Deep Foundations Institute Annual Meeting Cleveland, Ohio, November 1983By Clyde N. Baker
Foundations for the Sohio Corporate Headquarters in downtown Cleveland have column loads of 11,400 kips, which increase to 15,000 kips with wind loading. An extensive exploratory program was conducted
Jan 1, 1984
-
Numerical Analysis in Assisting Crane Pad Design and Underground Utilities EvaluationBy Yazen Khasawneh, Yao Zhang
Upgrading and maintenance programs were proposed at a power generating plant in Indiana. To perform construction activities associated with the proposed upgrading and maintenance, a LR11350 crawler cr
Jan 1, 2019