Deep Excavation with Well Point Dewatering in Soft SoilBy Mihir B. Roy
"Coal transported by rail for Thermal Power Plant in Haldia, West Bengal, India, was to be received and stored in Coal Complex comprising of Wagon Tippler, Track Hopper, Junction Houses and network of
Jan 1, 2015
-
Value Engineering – Design Risk and Reward at Major Sport Arena ProjectsBy Peter Faust, Jeremy Zorne, Timothy Siegel, Diane Fiorelli
Professional sport venue construction follows a very simple rule. Once the decision has been made to move the team to a new place, construction shall begin immediately, so that not more than one or tw
Jan 1, 2018
-
Concrete Filled Steel Tubes for Deep Foundations of Transportation StructuresBy Charles Roeder, Amy Leland, Dawn E. Lehman
Concrete filled steel tubes (CFSTs) are composite members that are commonly used in many countries today. CFST components are used in the United States, but they are more common in Asia, in part becau
Jan 1, 2019
-
An Overview Of Augered, Cast In Place Piles In Florida - IntroductionBy Kirk A. Mcintosh
Augered, cast-in-place (ACIP) piles have been utilized in the United States for a wide range of projects since the 1950's. Due to the cast-in-place nature of the installation method (and lack of
Jan 1, 1997
-
Development Of Design Practice For Piles In Stiff Glacial TillBy Kenneth Gavin
Design practice for piles installed in Irish glacial till has developed in an ad-hoc manner, based on the results of un-instrumented load tests. This had led to designers using similar design paramete
Jan 1, 2009
-
Augered Pile World Record Depth within a Soil Mix BasementBy Andres M. Baquerizo, Jeremiah J. Filjones, Nicholas Feldt
The Estates at Acqualina located in Sunny Isles Beach, FL, is comprised of two, ocean-front, 50-story, luxury towers with podiums and villas. With city regulations now requesting that above-grade floo
Jan 1, 2019
-
Session 11 Jet Grouting IIBy George Burke
Of the three projects, particularly the extensive Nimitz II (downtown) project, a single system, which was part of the operation, was used to control the spoil. Spoil control was continuous with the w
Feb 10, 2003
-
Linking the Installation Response of Screw Piles to Soil Strength and Ultimate CapacityBy James P. Hambleton, Sam A. Stanier
A perceived advantage of screw-type foundations is the ability infer aspects of foundation performance from quantities measured or observed during installation, especially the installation torque. A p
Jan 1, 2019
-
Technical Note Evolution Of Top Of Pile Measurement Techniques In Deep Foundation Static Load TestingBy Jon Sinnreich
Ensuring the accuracy of collected data during deep foundation static load tests is of paramount importance. Typically, pile head displacements are measured relative to a purpose-built reference syst
Jan 1, 2009
-
Ground Improvement by a Combination of a Mixed-In-Place (MIPTM) Lattice Grid Wall and Stone Columns to Mitigate the Risk of Liquefaction and Lateral SpreadingBy Noreen Tarac, Pablo Forgoso, Philipp Schober
A multiple use storage facility building is being developed in the Philippines on a peninsula that was reclaimed in the 1990s without any soil treatment. The subsoil now consists of loose to medium de
Sep 8, 2021
-
Large Diameter Auger Cast Piles At Audi Field, Dc United's New Soccer StadiumBy Christophe H. Locussol
D.C. United, the professional soccer team located in Washington, D.C., completed a 20,000 seat capacity stadium in July 2018 named Audi Field. The project initially considered a foundation system cons
-
Results Of Dynamic And Static Load Tests On Helical Piles In The Varved Clay Of MassachusettsBy Jorge Beim
Helical Piles are increasingly being used to support and rehabilitate structures subjected to compressive axial loads. Traditionally, empirical correlations between installation torque and load capaci
Jan 1, 2012
-
PMF Remediation of Oxford DamBy Scott Dodds
"The Oxford Hydroelectric Station was a unique project that incorporated a variety of dam strengthening methods to stabilize the facility in order to meet the standards required by Federal Energy Regu
Jan 1, 2005
-
Boston Waterfront Redevelopment: Re-use Of Existing Pier Piles To House Future GenerationsBy John P. Briand III, Douglas J. Aghjayan, Robert E. Fosse
This paper highlights the successful pile load testing program for the redevelopment of Pier One in East Boston, Massachusetts. Pier One is a 5.4-acre parcel on a dormant waterfront site used in the 1
-
Investigating Reinforcing Effects of Soil-Cement Columns in Liquefiable Sand Using Dynamic Centrifuge TestsBy C. Guney Olgun, Mohammad Khosravi, Daniel W. Wilson, Deepak Rayamajhi, Scott A. Ashford, Shuji Tamura, Ross W. Boulanger
"Dynamic centrifuge tests were performed on unimproved and improved soil with soil-cement column models. The reinforcing effect of isolated soil-cement columns for reducing liquefaction potential and
Jan 1, 2015
-
Making Foundation Design Courses More Engaging and Effective for StudentsBy Evangelia Ieronymaki
Civil engineering education relies on traditional methods of teaching, comprising mostly of deductive instruction by presenting the theory, followed by applications. This paper presents an alternative
Jan 1, 2019
-
Designed, PDA Assisted Load Tested, And Constructed Pile Foundation Provides An Economical Foundation Solution - A Case HistoryBy Gregory A. Stephan
A case history of design, prediction, probe pile driving, and construction of a pile foundation for Building 3 of Waterside at Bay Beach Condominiums located in Fort Myers Beach, southwest Florida, is
Jan 1, 2003
-
Cost Analysis Of Multiline Ring Anchor Systems For Offshore Wind FarmBy Junho Lee, Leopoldo Bello, Mohammad Khan
Multiline ring anchor (MRA) was developed as a cost-effective solution for securing floating offshore wind turbines (FOWTs) to the seabed. Since FOWTs are placed in arrays compared to conventional oil
-
Innovations and Challenges during Urban Development – Shoring and Foundations of Canada’s Tallest Residential BuildingBy Shawna Munn, Nadir Ansari, Toben Jerry
With ever increasing demands on space in urban environments and smaller available footprints, buildings are being designed to increasing heights to meet the need. This case study discusses the increas
Jan 1, 2019
-
Installing And Testing Multi-bar High Capacity Rock TiedownsBy Andrew Pontecorvo, Steven Lowe, David Sposito
Buildings with large height-to-width ratios require foundations with significant uplift resistance. This paper presents a case study of the permanent rock tiedowns installed for One Manhattan West, a