    Hollow Core Bar Micropiles - Design Parameters Interpreted From 260 Load Tests

    By Jesús E. Gómez

    A recent bridge underpinning project provided a unique opportunity to obtain information on the load-deflection response of 260 hollow-core bar micropiles. All production micropiles were proof-tested

    Jan 1, 2007

  • DFI
    Port Orange Drilled Shaft Load Tests - Introduction

    By David K. Crapps

    The drilled shaft load tests at Port Orange were part of a demonstration project sponsored by the Federal Highway Administration (FHWA) and the Florida Department of Transportation (FDOT). Three load

    Jan 1, 1989

  • DFI
    Helical Piles With Grouted Shafts - A Case History

    By Shawn Downey

    A helical pile with in-situ grouted shaft was used to underpin the existing slab of a large retail store in the Edmonton, Alberta Canada area. The existing structural slab did not have the capacity to

    Jan 1, 2003

  • DFI
    Practice Of Large Diameter Stepped Section Bored Pile Foundation Of A Deep Water Bridge

    By Cen Guoji

    The foundation of bored pouring concrete pile have been adopted in the bridge engineering of China since early in the sixties. They demonstrated tremendous technical advantage and achieved notable eco

    Jan 1, 1991

  • DFI
    Installation Of Augered Cast-In-Place Piles

    By Michael Moran

    Typical ACIP Pile Rig [ ] Hollow Stem Auger ? Continuous flight auger ? 3 inch inside diameter pipe ? Auger diameters: 12, 14, 16, 18, 20, 22, 24, 30, and 36 inches ? Auger section lengths:

    Jan 1, 2005

  • DFI
    Use Of Installation Effort To Evaluate And Design Drilled Displacement Piles In Fine-Grained Soils

    By W. Morgan NeSmith

    A drilled displacement pile program was utilized for the expansion of an existing power plant in Cohasset MN adjacent to the Mississippi River. The drilled displacement (DD) pile is an innovative foun

    Jan 1, 2008

  • DFI
    Large Scale Jet Grouting And Deep Mixing Test Program At Tuttle Creek Dam

    By Mario Mauro

    Tuttle Creek Dam was constructed by the U.S. Army Corps of Engineers in the 1950?s on the Big Blue River in north-east Kansas. Since the dam is located in a seismic area, the safety of the dam was re-

    Jan 1, 2008

  • DFI
    Woodrow Wilson Bridge Cofferdams

    By Roderic A. Ellman

    The new Woodrow Wilson Bridge (WWB) will replace the existing bridge over the Potomac River to connect Alexandria, Virginia to Prince Georges County, Maryland. The new WWB will extend approximately 1.

    Jan 1, 2005

  • DFI
    Design And Load Test Of Micropiles In A Power Plant In Missouri

    By Bidjan Ghahreman

    A total of 120 micropiles were constructed for foundations of a new selective catalytic reduction (SCR) unit in a coal-fired power plant east of Kansas City, Missouri. Construction was performed unde

    Jan 1, 2009

  • DFI
    Practice Of Arranging Drilling Piles In Subsiding Grounds

    By Vladimir M. Korolev

    The field studies conducted at the experimental-production sites allowed to develop the technology of arranging drilling piles in loess subsiding grounds over 25 m deep and over 250 mm in diameter, to

    Jan 1, 2002

  • DFI
    Capacity Prediction Vs. Performance Of Driven Pre-Cast Pre-Stressed Concrete Piles In Chesapeake, Virginia

    By Emad Farouz

    This paper compares the predicted axial capacity of driven Pre-cast Pre-stressed Concrete (PPC) piles for the Lake Gaston Water Treatment Plant (LGWTP) using several design methodologies versus the ax

    Jan 1, 2007

  • DFI
    A Study Of Failure Mechanism And Uplifting Capacity Of Tension Pile Foundation ? Synopsis

    By K. J. Yang

    Based on investigations and model tests combined with pile foundation on Code compilation of drydocks, we present this report to give informations against uplift pressure of piles beneath floor of dry

    Jan 1, 2010

  • DFI
    Settlement Control Of A Road Embankment Using Vertical Drains

    By Wei Tu

    A grade separation was required to allow uninterrupted traffic crossing for a busy rail spur and a county road. The grade separation was achieved by creating a 30-foot (9-meter) high embankment that

    Jan 1, 2009

  • DFI
    Compaction-Induced Lateral Earth Pressures And Vertical Shear Forces Acting On Non-Moving Retaining Walls

    By George M. Filz

    Restrained basement walls and unrestrained but massive concrete walls on rock foundations experience very small movements in response to lateral earth pressures. Such walls are often designed using at

    Jan 1, 2003

  • DFI
    Cut-and-Cover Excavation Challenges

    By Sitotaw Y. Fantaye

    "The first segment of the Second Avenue Subway extension is approaching construction completion. The new extension will operate along Second Avenue from 96th Street to 63rd Street, where it will diver

    Jan 1, 2016

  • DFI
    Comprehensive QA/QC Integrity Testing Using Thermal Integrity Profiler

    By Brad W. Taylor

    "During the past several months, I have introduced to civil and structural engineers an innovative solution for the integrity testing of concrete using the Thermal Integrity Profiler (TIP) Wire Cable

    Jan 1, 2017

  • DFI
    Ground Improvement Resulting From Installation Of Drilled Displacement Piles

    By Timothy C. Siegel

    Drilled displacement piles (also known as augered cast-in-place displacement piles or augured, pressure grouted displacement piles) are installed by the displacement of soil and subsequent placement o

    Jan 1, 2007

  • DFI
    Analogy Between Analyze Of Pile And Penetrometer Tip Resistance By Cavity Expansion Method

    By Farhad Elmi

    In this paper, a new procedure is used to find the bearing capacity of single piles and cone penetration resistance in soils. Although the procedure is mainly applicable to clay and sand using any pla

    Jan 1, 2002

  • DFI
    2100 L Street Underpinning & Support Of Excavation

    By Charles R. Conlon, Matthew J. Niermann

    This paper presents the underpinning and excavation support systems used for construction at 2100 L Street in Washington, DC. The excavation for the proposed building extended below bedrock, which pre

  • DFI
    Behaviour Of Laterally-Loaded Piles Centrifugal And Numerical Modelling ? Synopsis

    By W. H. Craig

    Techniques have been developed for installing model piles into beds of soil under high sustained acceleration levels aboard a centrifuge. These piles have been subjected to static and/or cyclic latera

    Jan 1, 2010