Planar Kinematics Of Dragline Digging For Efficient Machine ControlBy S. Frimpong, N. Demirel
Overburden excavation is an integral component of the surface mine production chain. The walking dragline is the most economic production equipment for overburden excavation in strip mining. Draglin
Jan 1, 2006
-
Stoval - For: A Stochastic Mine Evaluation Computer Program ? InformationBy Howard M. Wells
Investment in minerals development usually entails big financial outlays. which will remain at risk for a long time before the venture can begin to generate a return cash flow. Before 'committing
Jan 1, 1982
-
New Material Handling System For Heap Leach Stack ConstructionBy M. L. Clark
Advances in the recovery of gold from heap leaching are being made daily, but of all the systems vital to the maximum recovery of gold from a leach pile, none is more important than the methods used t
Jan 1, 1988
-
Optimal Determination Of Dig Limits For Improved Grade ControlBy Karl P. Norrena, Clayton V. Deutsch
Ore and waste cannot always be visually separated. The distinction between ore and waste may need to be made on the basis of blasthole sampling. Hand drawn dig limits or computer-generated contour lin
Jan 1, 2002
-
Controlling Ventilation For Safe Escape From Coal Mine FiresIf a fire occurs outby an underground coal mine section, the immediate safe evacuation of miners from the working section should always take precedence. Unfortunately, in many cases, the dedicated esc
Jan 1, 1997
-
Copper Recovery From Reverberatory Slag At White Pine ? IntroductionBy Richard H. Johnson
White Pine Copper Company began operating a plant designed to recover copper matte particles from its discarded reverberatory furnace slags in April, 1972. Seasonal operation, generally the months of
Jan 1, 1975
-
Integrated approach for predicting mining subsidence in hilly terrainBy Y. Luo, S. S. Peng
Based on the concept of slope-stability analysis, a formula for determining an important parameter required in the mathematical model for the prediction of mining subsidence in hilly terrain is propos
Jan 1, 2000
-
Golden Jubilee Resin-In-Pulp Plant for Gold RecoveryBy Chris A. Fleming, Daan Seymore
The Golden Jubilee Mine in South Africa is the first mine in the Western World to introduce resin-inpulp technology for the recovery of gold from a cyanide-leached slurry. Located in the Eastern Tran
Jan 1, 1990
-
A Failure Criterion for Coal Seam at Longwall MiningBy A. Zorychta, T. Cyrul, Z. Kleczek
INTRODUCTION Underground mining causes disturbances of the primary state of stresses. Resulting from those disturbances a loss of stability of rocks that surround excavation may occur interrupting
Jan 1, 1986
-
Examination of Support Methods for Block Caving Slusher DriftsBy Mark Board
INTRODUCTION As the world's supply of near-surface metalliferous ore bodies is depleted, more emphasis must be placed upon mechanized bulk systems of underground mining. In particular, block ca
Jan 1, 1982
-
Current Methods Of Objective Ground Assessment For Underground ConstructionBy Graham E. Rawlings
Geotechnical investigations for underground projects are subject to a variety of constraints, including factors such as accessibility, geological complexity, thickness of oberburden and finance. As a
Jan 1, 1983
-
Technical Note - Alternative Method Of Blending For Sulfur ComplianceBy S. Hicks
This technical note describes an alternative procedure that can be used in linear programming calculations where the compliance limit of lbs SO2/million Btu for the blending coal is subject to change.
Jan 1, 1998
-
Computer Uses For Coal Mine Engineering And Geology ? IntroductionBy L. Michael Kaas
In recent years a number of data processing and analytical techniques have proven to be useful to engineers and geologists in various segments of the mineral industries. Petroleum companies were among
Jan 1, 1973
-
Software For Hydrologic Monitoring Of In Situ Leaching OperationsBy Peter K. Mathison
The U. S. Department of Interior, Bureau of Mines (Bureau) is developing a hydrologic monitoring system for in situ leaching operations. A working prototype of this system was installed and tested at
Jan 1, 1992
-
6. Computer-Based Consultation System for Mineral Exploration ? IntroductionBy Peter E. Hart
The search for mineral deposits is a difficult high-risk enterprise whose likelihood of success is influenced by a great many factors. Among the most important of these factors are the knowledge and j
Jan 1, 1979
-
Mining And Enviromining Law For Industrial Minerals And RocksWith the advent of the environmental "green" movement of the 1960s, eventually leading to Earth Day 1970, Congress responded by passage of the National Environmental Policy Act (NEPA), 1970. NEPA gave
Jan 1, 1994
-
Probability-Assigned Constrained Kriging For Precious Metal Reserve ModelingBy G. Pan
The production data of many mines have not reconciled geostatistical estimations based on exploration and development drilling. The discrepancies in recovered metals are sometimes as large as 30%. A n
Jan 1, 1995
-
Underground Construction Applications Of GroutBy William R. Nash
Case histories of water problems in underground mine shafts and tunnels are outlined to illustrate varying degrees of sophistication in grouting techniques currently applied in such construction. The
Jan 1, 1984
-
Cost Model for Transitioning from Surface to Underground MinesBy V. O. Tenorio, A. M. Sanzana
"INTRODUCTION This report summarizes a research about mines which are transitioning from surface to underground mines. It is a guide to make strategic decision in these increasing amount of mines. Cap
Jan 1, 2016
-
Flowsheet Changes For Decreased Moisture Of Concord Mine CoalBy J. D. Allen
The Concord Mine Coal Preparation Plant of United States Steel Corporation, located near Bessemer, Alabama, began operations in June, 1950. The basic cleaning circuit consisted of a Chance Cone for cl
Jan 1, 1966