    Overcoming Constructability Challenges for Drilled Displacement Pile Installation in Difficult Geology

    By A. Rod Kern, Michael A. McNicholas, Yaser Taheri

    Deep foundations were required for construction of an 18,000 ft2 (1,672 m2) 4-story office building and an adjacent 23,750 ft2 (2,206 m2) 5-story parking garage in Queens, New York due to an existing

    Jan 1, 2019

  • SME
    Overcoming Design Challenges on the Ohio River Tunnel to Improve Water Quality in Pittsburgh, PA - NAT2024

    By Zhenqi Cai, Mike Lichte, Kimberly Kennedy

    The Ohio River Tunnel is the first of three combined sewer overflow tunnels to be constructed under Allegheny County Sanitary Authority's Clean Water Plan. The project consists of a total of approxim

    Jun 23, 2024

  • DFI
    Overcoming Grouting Difficulties During Retaining Wall Stabilization

    By Jared M. Green

    This paper presents the wall stabilization design and implementation for a 541 linear ft masonry and concrete gravity-type retaining wall flanking the west perimeter of a 7.37 acre parcel in Bronx, Ne

    Jan 1, 2011

  • AUSIMM
    Overcoming implicit modelling software limitations using Python scripting – an innovative geological modelling workflow for George Fisher Mine, Queensland, Australia

    By L Bertoss, D Carvalho

    In the last decade, the use of advanced implicit modelling software/algorithms in mineral resource workflows has become a best practice in the mining industry. In most cases, these workflows can easil

    May 24, 2023

  • SME
    Overcoming local conflicts and production needs related to mining. Social impact assessment and local participation

    By G. Balletto, C. Furcas

    "The mineral raw materials industry is a key-component of the Gross Domestic Product of industrialised economies, closely related to both the building and the industrial sectors. Despite this, at loca

    Jan 1, 2011

  • SME
    Overcoming Massive Squeezing Ground Utilizing Curved Tunnel Face and Full-Face Excavation with Early Ring Closure

    By Hiroyuki Tamaru, Futoshi Kusumoto, Kosuke Tanimura, Atsuyuki Kimura

    "SUMMARY The Hachinoshiri tunnel is a 2,469 m long two-lane road tunnel on the Chubu-Odan Expressway. Since more than 70% of the total tunnel length consists of low strength rock masses the competence

    Jan 1, 2016

  • SME
    Overcoming Preconceptions For A Successful launch Of Autonomous Haulage

    By James Humphrey

    There is a natural resistance to change in any form. When it comes to implementing a game-changing technology like autonomous haulage on an operating mine site, the resistance can at times appear insu

  • SME
    Overcoming Sustainability Challenges for Design and Construction of Urban and Long-Distance Tunnels - NAT2024

    By Bernd Hagenah, Eric C. Wang

    New tunnels of significant alignment lengths such as mountain tunnels, base tunnels, as well as beneath urban centers pose unique environmental challenges. This paper highlights key environmental cons

    Jun 23, 2024

  • DFI
    Overcoming the Challenges Endured by the Quality Assurance and Quality Control Teams during the Construction of a Deep Cutoff Wall in East Alton, Illinois

    By Raffaella Granata, Wesley Schmutzler, Matteo Bertoni

    "The Lower Wood River Levee system, at the confluence of the Wood River Creek and the Mississippi River, in East Alton, Illinois, has been plagued with underground seepage and, in 2010, remediation wa

    Jan 1, 2017

  • AUSIMM
    Overcoming the Challenges of Managing Tailings from Iron Ore Mining in Western Australia

    By D R. Anstey

    The growing demand for iron ore from Western Australia has led to an increased focus on the development of magnetite and lower grade iron ore deposits. The need to process and beneficiate the ore from

    Jul 11, 2011

  • TMS
    Overcoming The Challenges Of Plantwide Control

    By John A. Herbst

    Plantwide control of mineral processing operations has long been sought for its potential benefits. These benefits include minute-to-minute optimization, reacting to disturbances in ore characteristic

    Jan 1, 1996

  • TMS
    Overcoming the Challenges of Plantwide Control (1c61443a-08dc-4d11-b2ac-b217ab4e12e7)

    By John A. Herbst, William T. Pate

    "Plantwide control of mineral processing operations has long been sought for its potential benefits. These benefits include minute-to-minute optimization, reacting to disturbances in ore characteristi

    Jan 1, 1996

  • ABM
    Overcoming The Conflict Between Long Bof Refractory Lifetime And Efficient Bottom Stirring: A Case Study At Meishan Steel In China

    By Rainer Hüsken

    Over the last decades long BOF campaign lives have successfully been established due to improved quality of the refractory material and due to intensive use of slag splashing. On the other hand, steel

    Jul 30, 2018

  • SME
    Overcoming Underground Mining Space Constraints

    When most people think of coal mining, they envision men in soot-covered clothes and hard hats digging at deposits in deep underground caverns. These mental images commonly include coal cars rumbling

  • SME
    Overestimation Of Acid Generating Potential (AGP) In Alunite-Bearing Waste Rock

    By A. S. Hall

    Significant pyrite often does not dissolve in the Sobek (1978) nitric acid extraction; therefore, the standard conservative approach is to estimate pyrite using sulfur present in the sum of the nitric

    Jan 1, 1999

  • CIM
    Overestimation of oil sands mining reserve caused by an archaic algorithm

    By L. Chunpongtong

    The Athabasca oil sands mineable resource is located in northeastern Alberta, Canada. In oil sands mining, the ore zone is regulated to have a minimum mining thickness of 3 m and a cutoff grade of 7 w

    Jan 1, 2014

  • SME
    Overexcavation Risk Management During Pressurized Face Tunneling in the Pacific Northwest - RETC2023

    By Ulf Georg Gwildis

    Overexcavation and ground loss events during pressurized-face TBMadvance in soft ground can result in unplanned deformations above the tunnel and damage to existing infrastructure. Successfully managi

    Jun 13, 2023

  • SME
    Overflow Ball Mill Sizing: A Shared-Time Computer Program ? Introduction

    By Duncan M. Lamb

    Commercial computer "time-sharing" is a new and powerful tool for the engineer. It is a system of virtually simultaneous use of a digital computer by several individuals. Access to the computer is by

    Jan 1, 1969

  • AIME
    Overflow Crowd at Coal Division Sessions Takes Part in Lively Discussions

    By D. R. Mitchell

    MEETING for the thirteenth time in New York as part of the five-ring circus known as the Annual Meeting A.I.M.E., the Coal Division experienced a wartime boom in attendance. Technical sessions were cr

    Jan 1, 1943

  • CIM
    Overhead Protection Systems (OPS): Some Recent Applications

    By M. C. Walton, W. Roelofs

    ABSTRACT: In most cases, a refractory repair involves dealing with used refractory linings above shoulder height, defining these as overhead refractories. This paper details a method of personnel prot