Search Documents

  • SME
    Comminution Of Carbonate Minerals In A High-Pressure Roller Mill

    By E. Forssberg

    Studies have been carried out with the High Pressure Roller Mill, HPRM, to produce calcium carbonate minus 10 micron. This paper presents the optimization of the specific grinding force of the HPRM sy

    Jan 1, 1996

  • AUSIMM
    Comminution of Minerals on a Laboratory-size Choke-fed High-Pressure Roll Mill

    By Gutsche O, Kapur PC

    Experimental data on the production of fines as a function of specific grinding energy consumption show that in general the energy utilisation in a choke fed high-pressure roll mill is higher than i

    Jan 1, 1993

  • SME
    Comminution Of Minerals Under Compressive Loads In Confined Particle Beds

    By D. W. Fuerstenau

    One of the more energy-efficient methods for size reduction, namely particle-bed comminution under high compressive loads, was employed to grind eight minerals and ores, using up to 250 MPa pressure.

    Jan 1, 1993

  • SAIMM
    Comminution Research At The University Of Cape Town

    Comminution is a vital part of minerals extraction, and therefore of the South African economy. The high cost and throughput-limiting nature of comminution forms a strong motivation for research direc

    Jan 1, 1998

  • CIM
    Comminution, Flotation and Gravity Separations

    By James A. Finch

    "I offer a personal view of what the next 30 years holds for mineral processing. Re-stating that mineral processing will remain a vibrant industry in raw material production, growth opportunities in w

    Jan 1, 1998

  • SME
    Comminution-Based Powders for Technical Ceramic Applications

    By K. S. Narayanan, Marcia L. Bartges, K. S. Venkataraman

    The starting powders' physicochemical properties and consistency are essential for technical ceramic products to meet their performance specifications. The need for finer and more consistent powd

    Jan 1, 1992

  • AUSIMM
    Commissioning - From a Project Manager's Viewpoint

    Commissioning is one of the many phases of a project, it has inter-dependencies with the other phases, as they have amongst themselves, and has its own terminology and distinctive features. Commis

    Jan 1, 1986

  • AUSIMM
    Commissioning a Large Coal Blending and Preparation Plant

    The Curragh coal mining operation was designed and constructed to produce two coals initially at a rate of 4.3Mtpa. These are a high thermal energy steam coal primarily for domestic electricity ge

    Jan 1, 1986

  • SME
    Commissioning And Evaluation Of 11.000 H.P. Variable Speed Sag Mill Gearless Drive At Chuquicamata Concentration Plant

    By H. Salamanca

    The electric operation and design features of the 11.000 H.P. variable speed SAG mill gearless drive is presented. The function of the frequency converter, control system drive and lubrication systems

    Jan 1, 1991

  • AUSIMM
    Commissioning and Operating an Autogeneous Mill at Karowe Diamond Mine

    By N A. Sikwa, L M. van Niekerk, G N. Ndlovu

    In June 2012, Lucara Diamond Corporation officially commissioned its Karowe Diamond Mine in Letlhakane, Botswana. The processing plant circuit incorporates variable speed autogeneous milling, a first

    Jul 15, 2013

  • CIM
    Commissioning and Operating Experience with Gekko’s Gold Ore Treatment Plants

    By Tim Hughes, Steve Gannon, Jennifer Abols

    "In the past year, two very innovative gold ore processing plants have been designed, built and commissioned by Gekko Systems Pty Ltd. The first plant in Vietnam utilizes conventional crushing and bal

    Jan 1, 2007

  • CIM
    Commissioning and Operation of Milling Circuit at Santarita Nickel Operation

    The Santa Rita mine is located in north eastern part of Bahia in Brazil and is owned and operated by Mirabela Mineração do Brasil Ltda. Typical SABC circuit was designed as the preferred option for th

    Jan 1, 2012

  • AUSIMM
    Commissioning and Operation of the 800 TPH Heavy Medium Cyclone Plant at Mount Isa Mines Limited

    By Pease JD, Munro PD

    The heavy medium cyclone plant for the preconcentration of silver-lead-zinc ore prior to grinding and flotation was commissioned in August 1982. This paper details the measures taken to get the pl

    Jan 1, 1984

  • CIM
    Commissioning and Operation of the Ag Mills at the Aitik Expansion Project

    By S. Markstrom

    The Boliden AITIK copper mine is located 100 kilometres north of the Arctic Circle in northern Sweden. A pre-feasibility study was conducted in 2005 with the aim of increasing the capacity of the exis

    Jan 1, 2012

  • CIM
    Commissioning and Operation of the Copper Cliff Weak Acid Treatment Plant

    By T. Xue

    429 As part of Inco's S02 abatement project for its Sudbury operations, a weak acid treatment plant (W ATP) was commissioned at the Copper Cliff smelter in August of 2004 to treat the weak acid

    Jan 1, 2006

  • SME
    Commissioning And Operation Of The Mineral Park Concentrator

    By M. Gorman

    The Mineral Park Mine is an open pit copper-molybdenum mine located in northwestern Arizona, approximately 74 miles southeast of Las Vegas, Nevada. The property has been owned by the Duval Corporatio

    Jan 1, 2010

  • AUSIMM
    Commissioning and Optimisation of the Phu Kham Copper-Gold Concentrator

    By G Harbort, T Georgiev, M Phillips

    Phu Bia Mining Ltd, a subsidiary of Pan Australian Resources Ltd owns and operates the Phu Kham copper concentrator located in the Xaysomboun District, Lao PeopleÆs Democratic Republic. Construction a

    Jan 1, 2009

  • AUSIMM
    Commissioning and Process Development of Pipeline and Port Operations at Pasminco Century

    By D Hodder, M Hoskins, A Rofe

    Pasminco Century MineÆs slurry pipeline was commissioned in November 1999. It currently transports zinc and lead concentrate slurries in batch form to the Port facility, 304 km away in the Gulf of Car

    Jan 1, 2003

  • CIM
    Commissioning And Ramp Up Of The Hpgr Circuit at Newmont Boddington Gold

    By Steven Hart

    In September 2009, Newmont began the commissioning of a 3 stage crushing and milling circuit at its Boddington Gold Operation in Western Australia. The Boddington ore has been recognized as one of the

    Jan 1, 2012

  • CIM
    Commissioning and Ramp Up of the HPGR Circuit at Newmont Boddington Gold (Newmont Boddington Gold’s Processing Facilities)

    By Brendan Parker, Tyron Rees, Steven Hart, Abba Manesh, Ian Mcgaffin

    "In September 2009, Newmont began the commissioning of a 3 stage crushing and milling circuit at its Boddington Gold Operation in Western Australia. The Boddington ore has been recognized as one of th

    Jan 1, 2012