Search Documents

  • CIM
    Control Blasting for Slope Stability at the Adams Mine

    By Barry J. Morash

    The over-all slope angle of between 55 and 60 degrees at the Adams Mine necessitates control blasting on the final pit walls. The control blasting techniques used are pre-shearing and buffer blasting.

    Jan 1, 1978

  • CIM
    Accurate assessment of the Hirakud smelter aluminium reduction cell thermal balance using only temperature measurements

    By M. Dupuis

    In the present study, the heat balance of the Hirakud smelter aluminium reduction cell has been accurately assessed using only a surface thermocouple and a pyrometer, As it is well known that using a

    Jan 1, 2004

  • CIM
    Opportunities for Energy Savings and Energy Recovery Using Indirect Heat Exchangers for Bulk Solids

    By Neville Jordison

    Indirect, gravity flow, heat exchangers have become a well established technology in mineral and metallurgical process plants. The technology is a conventional heat exchanger using high efficiency pla

    Jan 1, 2011

  • TMS
    Increasing Capacity and Productivity in the Metals Markets through Pneumatic Conveying and Process Injection Technologies (f2be4a35-8e36-4521-a0c5-66d30bc37b25)

    By M. E. Coleman, G. Money

    "Clyde Materials Handling is an established customer-driven solutions provider, which utilizes its knowledge, expertise and technologies to transform the production processes of its customers, who ope

    Jan 1, 2009

  • NIOSH
    OFR-11-77 The Correlation Of Mine Roof Failure With The Time Elapse Before Support Installation

    By Robert M. Cox

    The objective of this study was to determine if significant relationships exist between coal mine roof stability and the time roof is left unsupported. Additional factors such as geology, opening geom

    Jan 1, 1974

  • SME
    Real-World Improvement through Virtual Instrumentation at Oceanagold Haile (b3d97d8e-a1b0-4f54-9b98-1f700f983ef8)

    By C. Anderson, B. Schug, C. Cristoffanini, S. Nazari

    The Haile Gold Mine in South Carolina is increasing the automation level of their processing plant in order to improve operational stability. One step towards this goal is the application of a Digital

    Jan 1, 2019

  • SME
    A Survey Of Mine Ventilation Practices ? Introduction

    By Pierre Mousset-Jones

    A questionnaire was sent out to three classes of mines to determine the extent of the heat problem in U.S. and Foreign underground mines. The following list shows the replies received from this questi

    Jan 1, 1986

  • AIME
    Relations between Government Surveys and the Mining Industry - United States Geological Survey's Point of View on Relations between Surveys and the Mining Industry

    By G. F. Loughlin

    Nearly 55 years have elapsed since the U. S. Geological Survey was organized. During this period the mineral industries have grown from infancy or early childhood to well developed maturity, and some

    Jan 1, 1935

  • NIOSH
    RI 3707 Briquetting Subbituminous Coal

    By V. F. Parry, John P. Goodman

    "INTRODUCTION Review of Previous Work Many investigators and certain commercial interests have recognized that the briquetting process is a practical method to convert much of what is now considered u

    Jun 1, 1943

  • TMS
    Thermodynamic and Experimental Study on the Steam Reforming Processes of Bio-oil Compounds for Hydrogen Production

    By Kun Wang, Xinhui Li, Huaqing Xie, Qingbo Yu, Qin Qin

    "Three typical model compounds of bio-oil (ethanol, acetone and phenol) were studied in the steam reforming process for hydrogen production. In the thermodynamic analysis, the three componds showed th

    Jan 1, 2014

  • CIM
    Discovery and technological change: the origins of steelmaking at Sydney, Nova Scotia

    By Kris Inwood

    "In 1879, when the Dominion government initiated its controversial program of industrial promotion, iron smelting in Canada was limited to one company producing coke iron on the mainland of Nova Scoti

    Jan 1, 1999

  • CIM
    Secondary Blasting and Car Loading at Flin Flon

    By H. A. Kramer

    The Flin Flon mine is at present hoisting 5,000 tons of ore daily. In 1943, a peak production of 6,188 tons daily was maintained. Before discussing secondary blasting, it is felt that a short review o

    Jan 1, 1946

  • SME
    Pre-Mining Planning For Environmental Control In Surface Coal Mines

    By R. V. Ramani

    Minerals, together with agricultural and forestry products, are the primary source of wealth produced in the United States. Although the production of minerals requires only a small fraction of the st

    Jan 1, 1977

  • TMS
    Design And Construction Of The Noranda Converter At The Borne Smelter

    By Michel Boisvert

    Noranda Metallurgy is presently completing construction of the new Noranda Converter (NCV) at its Home Smelter in Rouyn-Noranda. This capital investment of CDN$56M is the continuation of the Emissions

    Jan 1, 1998

  • SME
    Disaster Averted After MTBM/Active Gas Main Collision - Utilizing Captivating Case Histories to Educate Stakeholders with Regards to Tunneling in Urban Environments

    By Rory P. A. Ball, Mark Briggs, Martin Dix

    "Tunnel professionals should inform project stakeholders on the reality that tunnel projects are not 100 percent devoid of the need for excavations or public inconveniences during both design and cons

    Jan 1, 2016

  • SME
    Analysis Of Reported Ventilation Costs For Uranium Mine Radon Daughter Control

    By Robert C. Bates

    Published information discussing uranium mine radon daughter controls and related costs was examined and used to develop an estimated (projected) cost per ton for any level of control. Results show a

    Jan 1, 1983

  • CIM
    Fabrication-Induced Degradation and Safety Assessment for Pipelines during Service (d46b60f3-6ad7-4dd3-96b6-360981a83f59)

    By A. N. Kumar

    Two fabrication stages in the manufacture of pipelines are identified as causing significant deterioration of the steel plates, namely cold bending and welding. The objectives of this work include qua

    Jan 1, 2005

  • SME
    Open Pit Equipment Selection And Maintenance (78fec7f3-6239-4b59-9364-cdb682576ffa)

    By Frank H. Buchella

    Principal factors influencing equipment selection can be grouped into five basic categories. Tonnage Requirements, Ore and Waste Loading, transporting, and ground preparation equipment are lar

    Jan 1, 1973

  • NIOSH
    OFR-139-77 Development Of A New Dust Sampling Pump ? Section A ? Introduction And Summary ? 1. Introduction

    By S. Vennos

    As a result of Synopsis 73-16 Dynadyne responded with an unsolicited proposal offering the Bureau of Mines to develop an ultra-low volume coal mine dust personal sampler. In the ensuing technical disc

    Jan 1, 1975

  • NIOSH
    IC 6951 Progress Report 4 On Investigation Of Detachable Rock-Drill Bits ? Introduction

    By McHenry Mosier

    This is the fourth progress report in the series on the use of detachable rock-drill bits in the metal mines of the United States. It contains comparative statistics and costs or drilling at eight min

    Jan 1, 1937