New Wembley National Soccer Stadium, London Piled Foundations: Design, Construction and LogisticsBy Max Gwynn, Tony Suckling
"The new Wembley Stadium is the most spectacular soccer stadium in the world, built to the highest specifications, using the latest technology and offering visitors an unrivalled match-day experience.
Jan 1, 2008
-
Strain Gauge Interpretation Using Automated Collection Systems and the Accuracy of Using Extrapolated Modulus vs Constant Modulus of a Pile, Along With the Importance of a Detailed QA/QC ProgramBy Michael A. McNicholas
"Deep foundations utilize the varying soil conditions to provide the most cost-effective or practical scope for a given jobsite. Once the scope has been determined and the engineering applied, the ele
Jan 1, 2017
-
Innovative Non Encroaching Retaining WallBy Dino Kartofilis, Rick Deschamps, Giovanni (John) Bonita
"Anew condominium complex in Arlington, Va., presented some formidable constraints. One was the requirement for a permanent retaining wall to support a 48.5-ft (15-m) cut and an existing 16- story bui
Jan 1, 2009
-
Deviations From Design Impact Performance Of An Aggregate Pier Supported EmbankmentBy Jay L. Hodkinson
Replacement of an aging twin span river crossing in Vermont required a temporary bridge to accommodate traffic during construction. Soils beneath the temporary approach embankment consisted of very s
Jan 1, 2011
-
“Special Application Of Micro-Piles” For The Construction Of A Bridge Well FoundationBy Nagarajkumar BV
Pavai-and TeampT JV started working on the project T49A, Sumbar J & K State as part of slope and earth stabilization for ongoing Banihal - Katra Railway Connection Project. This project has several tu
Nov 1, 2022
-
Confined Space And Inner-City Projects – Future Challenge And Opportunity For Diaphragm WallingBy Alexander Blatt, Franz-Werner Gerressen
Diaphragm walls are known as underground structural elements commonly used as retention systems for excavation pits and shafts and permanent foundation walls or elements. One can anticipate that globa
Nov 1, 2022
-
Design Method For Bridge Abutment Foundation Piles Subjected To Lateral Earth Pressure ? SynopsisBy T. Matsui
Many existing bridge abutments on the soft ground laterally move and their many damage examples have been reported. An essential cause for the troubles of the lateral movements may be the lack of exam
Jan 1, 2010
-
Rocky Mountain Arsenal Section 36 Lime Basin Soil Remediation Project – Seepage BarrierBy A. David Miller, Douglas M. Barber
"The Rocky Mountain Arsenal was used by the military to produce chemical warfare agents and incendiary munitions for use during World War II and later by private companies for the production of indust
Jan 1, 2015
-
Drilled Shaft Design For Noise Wall Barriers Along I-20 In Columbia, SCBy Anil Bhandari
Using subsurface data collected at each drilled shaft location is an ideal approach for conducting drilled shaft design. However, conducting subsurface tests at each drilled shaft location and subseq
Jan 1, 2011
-
The Influence Of RC Nonlinearity On P-Y Curves For CIDH Bridge PiersBy Leonardo Massone
The p-y method is one of the most popular methods in pile design and has been calibrated for various boundary conditions using numerical and experimental studies during recent years. Most studies on r
Jan 1, 2012
-
Pile Diameter Effects On Initial Modulus Of Subgrade Reaction For Laterally Loaded PilesBy Hubert Law, Amin Rahmani
This paper evaluates the effects of pile diameter on the initial modulus of subgrade reaction and proposes modifications to the subgrade reaction moduli that are commonly used in the current state of
-
Challenges Of Earthen Cofferdam In Deep Excavations For Waterfront Structures, A Case StudyBy Balasubramani M., Ramana P. V., Bairagi K.
This paper is a case study of an earthen Cofferdam, constructed for a deep excavation at Intake location in river Aaundha, Maharashtra, India. A 12 m (39 ft) deep excavation was made to construct the
Nov 1, 2022
-
Construction Of The Main Tower Pier Caissons For The Greenville Bridge In MississippiBy F. Keith Jacobson
To be involved in the construction of a deep dredged caisson for a major bridge pier is one of the most rewarding and professionally challenging experiences one can have in the bridge construction bus
May 11, 2007
-
Construction Of The Main Tower Pier Caissons For The Greenville Bridge In MississippiBy F. Keith Jacobson
To be involved in the construction of a deep dredged caisson for a major bridge pier is one of the most rewarding and professionally challenging experiences one can have in the bridge construction bus
Jan 1, 2013
-
Piling Design and Construction Codes and Standards for Buildings A United States PerspectiveBy Rudolph P. Frizzi
"Abstract Pile design for building structures in the United States is typically performed by: 1) investigating and assigning engineering parameters to the respective ground bearing materials, 2) calcu
Jan 1, 2014
-
New Ground Freeze Method for Groundwater Cutoff below Foundation Excavations in Permeable SoilsBy Daniel W. Mageau, Larry W. Applegate, Aaron K. McCain
"An innovative method of ground freezing was successfully tested to create a “dry” excavation condition for a new building foundation at a site in downtown, Miami, Florida. The subsurface conditions i
Jan 1, 2015
-
University Of Minnesota Football Stadium Down Hole Pile: Innovative Solution For Difficult ConditionsBy Eric J. Pederson
The down hole hammer is widely used in specialty geotechnical construction. The common uses include tie-back anchor installation, micropile installation, and general soil/bedrock drilling operations.
Jan 1, 2008
-
Seismic Stability Analysis of Seepage Control Measures for Levees in Central Valley, CaliforniaBy Zia Zafir
"Levees in the central valley of California are primarily for flood control purposes and thus are subjected to infrequent hydraulic loading. The primary concern for these levees is their instability d
Jan 1, 2016
-
Holistic Thermal Assessment And Control Of Ground Freezing For A New Underground StationBy Christian Leble, Dr. -Ing. Jakob Vogelsang, Dr. -Ing. Oksana Solt, Dipl. -Ing. Joachim Meier, Dr. -Ing. Wolfgang Orth
In the course of closing the gap between the Brandenburg Gate and Alexanderplatz, the Museum Island station was built by Implenia Construction GmbH. The tunneling for the platform hall took place on a
May 1, 2022
-
Design And Construction Of Integral Drilled Shaft - Columns For The Boscawen-Canterbury BridgeBy Frederick C. Rhyner
Drilled shafts have become an economical foundation choice for bridges in the northeast United States, especially when they can be constructed over water without the use of cofferdams. For the Boscaw
Jan 1, 2004