Search Documents

Sort by

  • AIME
    Engineering Foundation Fund Increases

    A GIFT of $10,000 to the endowment of Engineering Foun-dation, made by the Central Hudson Gas and Electric Corporation, has been announced. In transmitting this gift T. R. Beal, president of the corpo

    Jan 4, 1928

  • DFI
    Engineering Foundation Support For Las Vegas Strip's Tallest Hotel Casino

    By Nicholas P. Gura

    This paper presents the analysis, design, and load test program results for drilled shafts to support a 70-story hotel tower and associated 10 story podium structures located in Las Vegas, Nevada. A

    Jan 1, 2007

  • AIME
    Engineering Geologic Investigations Of Rock Heterogeneity

    By Milan Matula

    One of the main characteristics of the development of rock mechanics in some countries is a close cooperation between experts in rock mechanics and workers in related fields, including soil mechanics

    Jan 1, 1970

  • SME
    Engineering Geological And Geotechnical Aspects Of Surface Coal Mining ? Introduction

    By Brian Stimpson

    A recent study by the National Academy of Engineering concluded that if the U.S. Coal Industry is to double production by 1985 it must open 30 new 2,000,000 tons per year surface mines in the eastern

    Jan 1, 1976

  • SME
    Engineering Geological Mapping And Computer Assisted Data Processing For Tunnels At The Rogers Pass Project, British Columbia

    By Dan G. Wasyluk, Meryl J. Klassen, Tony J. Morris, Clive H. MacKay

    The Rogers Pass Project in British Columbia has involved the construction of two railway tunnels totalling 16.6 km and a 345 m deep shaft. Systematic geological mapping was carried out at four heading

    Jan 1, 1987

  • SME
    Engineering Geology and Cavern Design for New York City

    By Christopher Snee

    ??care has to be taken that the design is driven by sound geological reasoning and rigorous engineering logic rather than by the very attractive images that appear on the computer screen.??Hoek 1999

    Jan 1, 2008

  • CIM
    Engineering Geology Considerations and Approach in Assessing the Stability of Rock Slopes

    By Douglas R. Piteau

    "Assessing the stability of a slope cut in rock is basically a problem of engineering geology - geology, because it involves a sound understanding of the important aspects of geology, such as geologic

    Jan 1, 1972

  • SME
    Engineering Geology of Barrick Goldstrike Mines’ Betze Pit

    By Michael R. Smith

    Barrick Goldstrike Mines Inc.’s Betze open pit is located at the north end of the Carlin Trend, in Eureka County, NV. Ten open pit gold mines exist on the trend, which strikes northwesterly, through

    Jan 1, 1994

  • SME
    Engineering Geology Of Betze/Post Pit Eureka County, Nevada, USA

    By M. R. Smith

    Barrick Goldstrike Inc.'s Betze/Post Open Pit is located at the north end of the Carlin Trend, in Eureka County, Nevada, U.S.A. (see location Map, Figure 1). About ten open pit gold mines exist o

    Jan 1, 1993

  • SME
    Engineering Geology Of St. Louis Co., Missouri

    By John D. Rockaway

    This report and accompanying engineering geologic map describe the generalized engineering geology of St. Louis County, Missouri for use in determining the most efficient, economical, and environmenta

    Jan 1, 1970

  • SME
    Engineering Geology Of The Manapouri Power Project, New Zealand

    By B. G. Hicks

    The Manapouri Power Project is located in New Zealand's South Island Fiordland. The project is being constructed for the New Zealand Ministry of Works. Construction began in 1963 and is scheduled

    Jan 1, 1968

  • SME
    Engineering Geology Of The Mica Underground Powerplant

    By Douglas D. Campbell, Alan S. Imrie

    INTRODUCTION Mica Dam is located on the Columbia River just downstream of the "big bend" of the Columbia, where it leaves the Rocky Mountain Trench and begins to flow southwards, approximately 85 m

    Jan 1, 1976

  • SME
    Engineering Geology Of The Proposed Trans-Sahara Road

    By Michal Bukovansky

    The Sahara Desert presents a serious obstacle to transportation route development in northwest Africa. Most highways and railroads are now limited to the coastal regions. A network of pioneer roads is

    Jan 1, 1970

  • SME
    Engineering Geology Problems Associated With Cavernous Formations ? Summary

    By Reese E. Mallette

    This paper makes five major points which may be contributions to the art of limestone sinkhole engineering. First, solution cavity development in limestones is dependent in great measure on pyrite con

    Jan 1, 1975

  • IOM3
    Engineering geomorphological mapping and opencast mining in unstable mountains - a case study

    By G. J. Hearn

    between particles in the classifying region is then

    Apr 1, 1995

  • SME-ICGCM
    Engineering Geophysics - Mine Subsidence Risk Assessment Study

    By Kanaan Hanna

    Abandoned mines pose a serious threat to public health and safety, as well as the environment. When active workings approach old mine workings, miners could encounter significant hazards. Additionally

    Jan 1, 2011

  • ISEE
    Engineering Geophysics for the Mining and Construction Industries

    By Douglas Rudenko

    Most engineers, mine operators, or contractors acknowledge the importance of having accurate subsurface information in order to plan a project or solve a problem. Conventional methods of exploring the

    Jan 1, 1998

  • AIME
    Engineering Graduates Find Jobs Plentiful

    By William B. Plank

    THERE are 19 pct fewer undergraduate and graduate mineral engineering students enrolled in the ECPD accredited schools of the United States this year than there were a year ago. The figures are: 8727

    Jan 1, 1952

  • AIME
    Engineering In Corporate Tax Determination

    By W. H. Davitt

    While it is true that taxes, especially income taxes, whether they be federal, state, or local, are not usually thought of as a "cost" of doing business, it is equally true that these tax costs do red

    Jan 7, 1974

  • AIME
    Engineering In Limestone Production

    By C. C. Griggs

    FROM its inception, a limestone quarry or mine should be under the direction of a capable engineer. Before it becomes a reality, he should outline the future results, plan the most economical methods

    Jan 2, 1925